§ 5327. Project management oversight
(a)
Project Management Plan Requirements.—
To receive United States Government financial assistance for a major capital project under this chapter or the National Capital Transportation Act of 1969 (Public Law 91–143, 83 Stat. 320), a recipient must prepare and carry out a project management plan approved by the Secretary of Transportation. The plan shall provide for—
(1)
adequate recipient staff organization with well-defined reporting relationships, statements of functional responsibilities, job descriptions, and job qualifications;
(2)
a budget covering the project management organization, appropriate consultants, property acquisition, utility relocation, systems demonstration staff, audits, and miscellaneous payments the recipient may be prepared to justify;
(5)
a change order procedure that includes a documented, systematic approach to the handling of construction change orders;
(6)
organizational structures, management skills, and staffing levels required throughout the construction phase;
(7)
quality control and quality assurance functions, procedures, and responsibilities for construction, system installation, and integration of system components;
(11)
periodic updates of the plan, especially related to project budget and project schedule, financing, ridership estimates, and the status of local efforts to enhance ridership where ridership estimates partly depend on the success of those efforts;
(b)
Plan Approval.—
(c)
Limitations.—
(1)
Limitations on use of available amounts.—
Of the amounts made available to carry out this chapter for a fiscal year, the Secretary may use not more than the following amounts to make contracts for the activities described in paragraph (2):
(2)
Activities.—
Paragraph (1) shall apply to the following:
(3)
Limitations on applicability.—
Subsections (a), (b), and (e) do not apply to contracts under this section for activities described in paragraphs (2)(B) and (2)(C).
(d)
Access to Sites and Records.—
Each recipient of assistance under this chapter or section 14(b) of the National Capital Transportation Act of 1969 (Public Law 91–143, 83 Stat. 320), as added by section 2 of the National Capital Transportation Amendments of 1979 (Public Law 96–184, 93 Stat. 1320), shall provide the Secretary and a contractor the Secretary chooses under subsection (c) of this section with access to the construction sites and records of the recipient when reasonably necessary.
(e)
Regulations.—
The Secretary shall prescribe regulations necessary to carry out this section. The regulations shall include—
(1)
a definition of “major capital project” for subsection (c) of this section that excludes a project to acquire rolling stock or to maintain or rehabilitate a vehicle; and
(2)
a requirement that oversight begin during the preliminary engineering stage of a project, unless the Secretary finds it more appropriate to begin the oversight during another stage of the project, to maximize the transportation benefits and cost savings associated with project management oversight.
(f)
Financial Plan.—
A recipient of financial assistance for a project under this chapter with an estimated total cost of $1,000,000,000 or more shall submit to the Secretary an annual financial plan for the project. The plan shall be based on detailed annual estimates of the cost to complete the remaining elements of the project and on reasonable assumptions, as determined by the Secretary, of future increases in the cost to complete the project.