STATE OF MINNESOTA
IN COURT OF APPEALS
C5-00-130
Rice Lake Contracting Corp.,
Respondent,
City of Two Harbors,
Respondent,
vs.
Rust Environment and Infrastructure, Inc.,
n/k/a Earth Tech Consulting, Inc.,
Appellant,
GME Consultants, Ltd.,
Defendant.
Filed August 22, 2000
Affirmed as Modified
Davies, Judge
Lake County District Court
File No. C795257
Gregory T. Spalj, Tien T. Cai, Fabyanske, Westra & Hart, P.A., 920 Second Avenue South, Suite
1100, Minneapolis, MN 55402 (for respondent Rice Lake Contracting and respondent City of
Two Harbors)
Larry M. Nord, Orman & Nord, 1301 Miller Trunk Highway, Suite 400, Duluth, MN 55811 (for
respondent City of Two Harbors)
Robert J. Huber, Leonard, Street and Deinard, P.A., 150 South Fifth Street, Suite 2300,
Minneapolis, MN 55402 (for appellant)
Considered and decided by Halbrooks, Presiding Judge, Davies, Judge, and Peterson, Judge.
S Y L L A B U S
1. A conditional promissory note provides a basis for an indemnity claim by the maker of the note.
2. A party cannot recover prejudgment interest in an indemnity action when it has settled the claim
against it with a conditional promissory note that provided no liability for prejudgment interest.
3. A differing site-condition is not present when the subsurface conditions encountered do not
materially differ from foreseeable conditions.
O P I N I O N
DAVIES, Judge
Appellant challenges the trial court's legal conclusions regarding indemnity, differing site-conditions,
and damages. We affirm as modified.
FACTS
Respondent City of Two Harbors (Two Harbors) contracted with respondent Rice Lake
Contracting Corp. (Rice Lake) to improve Two Harbors' sewage-treatment plant. Two Harbors
had earlier hired appellant Rust Environment and Infrastructure, Inc. (Rust), and GME Consultants,
Inc. (GME), as consulting engineers on the project. After completing the improvement, Rice Lake
sued Two Harbors for breach of contract, claiming that Two Harbors owed it an additional
$2,166,750 for rock excavation. Two Harbors filed a third-party complaint against Rust and GME.
Rice Lake and Two Harbors then entered into a settlement agreement whereby Two Harbors paid
Rice Lake $200,000 and executed a conditional promissory note to Rice Lake for $1,585,402.
The note was payable only out of the proceeds, if any, from legal claims Two Harbors was to assert
against Rust and GME. Rice Lake agreed to pay for pursuing Two Harbors' suit against Rust and
GME and was granted full control over the case. The case has produced two previous appeals:
Rice Lake Contracting Corp. v. Rust Environment and Infrastructure, Inc., 549 N.W.2d 96
(Minn. App. 1996), review denied (Minn. Aug. 20, 1996), and Rice Lake Contracting Corp. v.
Rust Environment and Infrastructure, Inc., 1998 WL 148082 (Minn. App. 1998), review
denied (Minn. May 28, 1998).
On this third appeal, the main issue is whether Two Harbors' indemnity claims are limited to the
$200,000 that Two Harbors actually paid. Rust argues that a common-law indemnity rule allows
recovery only of amounts that have actually been paid or for which the indemnitee is unconditionally
liable.
At trial, the judge first determined that Rust's claim that the bedrock discovered at the site was a
differing site-condition failed, as a matter of law. (This ruling is also at issue in this appeal.) A jury
then found that Two Harbors incurred a $2,166,750 liability to Rice Lake under the construction
contract that Rust prepared for Two Harbors. The jury also found that $1,994,378 of that amount
should be paid by Rust because its negligence in preparing the contract and supervising
performance caused the city to incur this much of its liability to Rice Lake. Notwithstanding the
jury's verdict, the trial court entered judgment against appellant Rust for just $1,785,402 (plus
prejudgment interest), ruling that the settlement agreement between Two Harbors and Rice Lake
limited Rust's liability--and Rice Lake's recovery--to this amount (the conditional promissory note
plus the $200,000 paid).
The trial court denied Rust's motion for a new trial or amended findings. This appeal followed.
ISSUES
1. Did the conditional promissory note provide a basis for an indemnity claim?
2. Was the award of prejudgment interest proper?
3. Did the trial court err in rejecting the differing site-condition claim?
4. Was the jury damage award properly calculated?
ANALYSIS
This case involves statutory and contract interpretation, which are questions of law subject to de
novo review. Meister v. Western Nat'l Mut. Ins. Co., 479 N.W.2d 372, 376 (Minn. 1992).
I.
A right of indemnity arises when a party seeking indemnity has incurred liability due to a breach of a
duty owed to it by the one sought to be charged, and such a duty may arise by reason of a
contractual obligation. Altermatt v. Arlan's Dep't Stores, 284 Minn. 537, 538, 169 N.W.2d 231,
232 (1969). Indemnity usually requires that one party reimburse another entirely for its liability.
Zontelli & Sons, Inc. v. City of Nashwauk, 373 N.W.2d 744, 755 (Minn. 1985).
Under Minn. R. Civ. P. 14.01, a joint tortfeasor need not wait until it has made the actual payment
to bring an indemnity claim, but may institute a third-party action in conjunction with the original
claim. Grothe v. Shaffer, 305 Minn. 17, 25, 232 N.W.2d 227, 232 (1975). When such a
third-party action is brought, the indemnity claim is contingent on the outcome of the original action.
Id., 232 N.W.2d at 233.
In this case, instead of pursuing the original action between them, Two Harbors and Rice Lake
entered into a settlement agreement whereby Two Harbors paid Rice Lake $200,000 and executed
a conditional promissory note. The settlement allowed Rice Lake to step into Two Harbors' place in
pursuing an indemnity action against Rust. Success in that action was the condition on which the
note became payable.
This procedure is different from the usual approach with an indemnity claim, but indemnity is an
equitable doctrine that does not lend itself to hard-and-fast rules, and its application depends upon
the particular facts of each case. Zontelli, 373 N.W.2d at 755.
Rust argues that the settlement agreement limits Two Harbors' third-party indemnity claim against
Rust to the $200,000 Two Harbors actually paid to Rice Lake because, for indemnity purposes,
the conditional promissory note is not payment. Rust argues that common-law indemnity requires
actual payment. In support of this proposition Rust references a Restatement of Restitution
comment:
[W]here the secondary obligor [here Two Harbors] gives a negotiable instrument as
conditional payment he is not entitled to indemnity until the instrument has been paid
or he has become unconditionally liable to a transferee of the instrument. * * *
Before such time, the duty of the primary obligor [here Rust] has not been
discharged and the benefit to him cannot be measured.
Restatement of Restitution § 76 cmt. c (1937).
Rust is correct that liability could not arise from Two Harbors' conditional payment to Rice Lake.
But here, the payment ceased to be conditional once the jury determined, first, that Rice Lake was
entitled to $2,166,750 under its contract with Two Harbors and, second, that Rust's negligence
caused $1,994,378 of this obligation. Therefore, Two Harbors' claim against Rust is no longer
limited to the $200,000 actually paid by Two Harbors to Rice Lake; the promissory note became
unconditionally payable for indemnity purposes when Two Harbors' liability to Rice Lake and Rust's
liability to Two Harbors was established.
Furthermore, during the time the note remained conditional, no procedural rule barred Rice Lake
and Two Harbors from pursuing the indemnity claim. Were we to rule that such a bar existed,
parties in the position of Rice Lake and Two Harbors would be precluded from settlements, like
this one, that serve judicial efficiency by turning three-sided disputes into two-sided conflicts.
We note also that the issues Rust faced at trial after the Rice Lake-Two Harbors settlement were
precisely those it confronted before the settlement. There was some realignment of the parties, but,
at bottom, Two Harbors was simply put in the role of a neutral. In most cases, turning a party into a
neutral will simplify the trial.
II.
Rust also argues that prejudgment interest was improperly included in the judgment. The settlement
agreement limited Rice Lake's recovery to the amount of the conditional promissory note for
$1,585,402 plus the cash payment, without any reference to prejudgment interest. Neither Rice
Lake nor Two Harbors can now claim prejudgment interest on the damages award when Two
Harbor's conditional liability and therefore Rice Lake's recovery were capped by the promissory
note. See Summit Court, Inc. v. Northern States Power, Co., 354 N.W.2d 13, 15 (Minn. 1984)
(after party executes release and satisfaction of judgment, that party may not later claim
prejudgment interest). The trial court improperly awarded prejudgment interest and the judgment is
reduced by the amount of that interest award.
III.
Rust claims that it is entitled to a new trial on the issue of damages because the trial court erred in
determining, as a matter of law, that it was not entitled to an adjustment based on a differing
site-condition.
A differing site condition may generally be described as a subsurface or other
unknown physical condition at the site which differs materially from that indicated in
the contract or from that which is ordinarily encountered, which leads to a material
change in the cost of construction.
City of Morton v. Minnesota Pollution Control Agency, 437 N.W.2d 741, 743 (Minn. App.
1989).
To prevail on its claim of a differing site-condition, Rust must prove cumulatively that
(i) the contract documents must have affirmatively indicated or represented the
subsurface conditions which form the basis of the plaintiff's claim; (ii) the contractor
must have acted as a reasonably prudent contractor in interpreting the contract
documents; (iii) the contractor must have reasonably relied on the indications of
subsurface conditions in the contract; (iv) the subsurface conditions actually
encountered, within the contract site area, must have differed materially from the
subsurface conditions indicated in the same contract area; (v) the actual subsurface
conditions encountered must have been reasonably unforeseeable; and (vi) the
contractor's claimed excess costs must be shown to be solely attributable to the
materially different subsurface conditions within the contract site.
Weeks Dredging & Contracting, Inc. v. United States, 13 Cl. Ct. 193, 218 (Cl. Ct. 1987), aff'd
861 F.2d 728 (Fed. Cir. Sept. 2, 1988) (emphasis added). The elements are cumulative, not in the
alternative. Id.
Element (iv) in the above list of elements required to establish a differing site-condition is critical. It
is that the subsurface conditions actually encountered differ materially from the subsurface
conditions that had been indicated to exist in the contract area. There is here no genuine factual
dispute on this issue because the uncontested evidence showed: (1) GME's soil report contained the
result from a boring sample that indicated that one of the five soil exploration borings was unable to
advance despite 50 blow weights; (2) a GME engineer stated that based on these reports he would
expect bedrock at the site; (3) Rust defined rock for purposes of the project as a blow count in
excess of 50 blow weights with no penetration; (4) bedrock was found in prior construction
projects at the site; (5) Rust estimated that 800 cubic yards of rock excavation would be required
for the project; and (6) the bid form solicited separate unit prices for rock excavation.
The trial court did not err in determining that there was no genuine issue of fact and, as a matter of
law, Rust was not entitled to an adjustment based on a differing site-condition.
IV.
Rust finally argues that damages were improperly calculated, claiming the amount of the judgment
should be reduced by the actual cost of the rock excavation. The jury was instructed to deduct the
cost of the rock excavation from the damage award and presumably did so. The trial court properly
concluded that Rust is not entitled to have the cost of rock excavation subtracted from the
settlement agreement. To do so would give Rust double credit.
D E C I S I O N
The trial court did not err in ruling that the conditional promissory note became payable for
indemnity purposes after a jury determined the secondary and primary obligors' liability, or in finding
that a differing site-condition was not present. The trial court erred in awarding prejudgment interest
when the settlement agreement did not provide for payment of prejudgment interest. The principal
judgment amount of $1,785,402 is otherwise proper.
Affirmed as modified.
|