4280.149—Requirements after project construction.
Once the project has been constructed, the lender must provide the Agency periodic reports from the borrower. The borrower's reports will include the information specified in paragraphs (a) and (b) of this section, as applicable.
(a) Renewable energy projects.
For renewable energy projects, commencing the first full calendar year following the year in which project construction was completed and continuing for 3 full years, provide a report detailing the information specified in paragraphs (a)(1) through (7) of this section.
(2)
If applicable, documentation that any identified health and/or sanitation problem has been solved.
(b) Energy efficiency improvement projects.
For energy efficiency improvement projects, commencing the first full calendar year following the year in which project construction was completed and continuing for 2 full years, provide a report detailing the actual amount of energy saved due to the energy efficiency improvements.