285.709—When conducting onsite fabrication inspections, what must the CVA or project engineer verify?
(a)
To comply with § 285.708(a)(3), the CVA or project engineer must make periodic onsite inspections while fabrication is in progress and must verify the following fabrication items, as appropriate:
(4)
Fabrication procedures specified in the Fabrication and Installation Report, and adherence to such procedures;
(13)
Dimensional check of the overall structure, including any turrets, turret-and-hull interfaces, any mooring line and chain and riser tensioning line segments; and
(b)
For any floating facilities, the CVA or project engineer must ensure that any requirements of the U.S. Coast Guard for structural integrity and stability (e.g., verification of center of gravity) have been met. The CVA or project engineer must also consider: