250.1155—What information must I submit for sensitive reservoirs?

You must submit to the Regional Supervisor an original and two copies of Form MMS-127; one of the copies must be a public information copy in accordance with §§ 250.186 and 250.197, and marked “Public Information.” You must also submit two copies of the supporting information, as listed in the table in § 250.1167. You must submit this information:
(a) Within 45 days after beginning production from the reservoir or discovering that it is sensitive;
(b) At least once during the calendar year, but you do not need to resubmit unrevised structure maps ( § 250.1167(a)(2)) or previously submitted well logs ( § 250.1167(c)(1) );
(c) Within 45 days after you revise reservoir parameters; and
(d) Within 45 days after the Regional Supervisor classifies the reservoir as sensitive under § 250.1154(c).