170.474—Who conducts the project closeout?
The following table shows who must conduct the IRR construction project closeout and develop the report.
If the project was completed by . . . | then . . . | and the closeout report must . . . |
---|---|---|
(a) BIA | The regional engineer or designee is responsible for closing out the project and preparing the report | (1) Summarize the construction project records to ensure compliance requirements have been met;(2) Review the bid item quantities and expenditures to ensure reasonable conformance with the PS&E and modifications; (3) Be completed within 120 calendar days of the date of acceptance of the IRR. construction project; and (4) Be provided to the affected tribes and the Secretaries. |
(b) A tribe | Agreements negotiated under ISDEAA specify who is responsible for closeout and preparing the report | (1) Meet the requirements of ISDEAA;(2) Comply with 25 CFR 900.130(d) and 131(b) (10) and 25 CFR 1000.249 , as applicable; (3) Be completed within 120 calendar days of the date of acceptance of the project; and (4) Be provided to all parties specified in the agreements negotiated under ISDEAA. |