585.311—Project-related restrictions applicable to Youthbuild homeownership housing.
Where the award of a Youthbuild implementation grant includes the eligible activities of acquisition, architectural and engineering fees, construction, or rehabilitation of homeownership housing, and where the costs for these activities are to be funded, in whole or in part, with Youthbuild grant funds, the housing project shall be required to comply with the following Youthbuild project-related restrictions:
(a) Program compliance.
Each homeownership project meeting the requirements of this section shall comply with the requirements of the HOPE II or HOPE III program authorized under subtitle B or C respectively of title IV of the National Affordable Housing Act.
(b) Restrictions on conveyance.
Conveyance restrictions apply to Youthbuild homeownership housing projects meeting the requirements of this part. Ownership of the property may not be conveyed unless the instrument of conveyance requires a subsequent owner to comply with the same restrictions imposed upon the original owner for the balance of the 10 year period.
(c) Ten year restriction.
The restrictions listed in paragraphs (a) and (b) of this section shall remain in force for a period of not less than 10 years after construction completion and issuance of an occupancy permit for Youthbuild homeownership housing projects meeting the requirements of this part.