§ 2746. Conceptual and construction design
(a)
Conceptual design
(1)
Requirement
Subject to paragraph (2) and except as provided in paragraph (3), before submitting to Congress a request for funds for a construction project that is in support of a national security program of the Department of Energy, the Secretary of Energy shall complete a conceptual design for that project.
(2)
Requests for conceptual design funds
If the estimated cost of completing a conceptual design for a construction project exceeds $3,000,000, the Secretary shall submit to Congress a request for funds for the conceptual design before submitting a request for funds for the construction project.
(b)
Construction design
(1)
Authority
Within the amounts authorized by a DOE national security authorization, the Secretary may carry out construction design (including architectural and engineering services) in connection with any proposed construction project if the total estimated cost for such design does not exceed $600,000.