§ 415a-1. Budget treatment of costs of acquisition of major systems by the intelligence community
(a)
Independent cost estimates
(1)
The Director of National Intelligence shall, in consultation with the head of each element of the intelligence community concerned, prepare an independent cost estimate of the full life-cycle cost of development, procurement, and operation of each major system to be acquired by the intelligence community.
(2)
Each independent cost estimate for a major system shall, to the maximum extent practicable, specify the amount required to be appropriated and obligated to develop, procure, and operate the major system in each fiscal year of the proposed period of development, procurement, and operation of the major system.
(3)
(A)
In the case of a program of the intelligence community that qualifies as a major system, an independent cost estimate shall be prepared before the submission to Congress of the budget of the President for the first fiscal year in which appropriated funds are anticipated to be obligated for the development or procurement of such major system.
(B)
In the case of a program of the intelligence community for which an independent cost estimate was not previously required to be prepared under this section, including a program for which development or procurement commenced before December 13, 2003, if the aggregate future costs of development or procurement (or any combination of such activities) of the program will exceed $500,000,000 (in current fiscal year dollars), the program shall qualify as a major system for purposes of this section, and an independent cost estimate for such major system shall be prepared before the submission to Congress of the budget of the President for the first fiscal year thereafter in which appropriated funds are anticipated to be obligated for such major system.
(b)
Preparation of independent cost estimates
(1)
The Director shall establish within the Office of the Director of National Intelligence for Community Management an office which shall be responsible for preparing independent cost estimates, and any updates thereof, under subsection (a) of this section, unless a designation is made under paragraph (2).
(2)
In the case of the acquisition of a major system for an element of the intelligence community within the Department of Defense, the Director and the Secretary of Defense shall provide that the independent cost estimate, and any updates thereof, under subsection (a) of this section be prepared by an entity jointly designated by the Director and the Secretary in accordance with section
2434
(b)(1)(A) of title
10.
(c)
Utilization in budgets of President
(1)
If the budget of the President requests appropriations for any fiscal year for the development or procurement of a major system by the intelligence community, the President shall, subject to paragraph (2), request in such budget an amount of appropriations for the development or procurement, as the case may be, of the major system that is equivalent to the amount of appropriations identified in the most current independent cost estimate for the major system for obligation for each fiscal year for which appropriations are requested for the major system in such budget.
(2)
If the amount of appropriations requested in the budget of the President for the development or procurement of a major system is less than the amount of appropriations identified in the most current independent cost estimate for the major system for obligation for each fiscal year for which appropriations are requested for the major system in such budget, the President shall include in the budget justification materials submitted to Congress in support of such budget—
(A)
an explanation for the difference between the amount of appropriations requested and the amount of appropriations identified in the most current independent cost estimate;
(C)
an assessment of the consequences for the funding of all programs of the National Foreign Intelligence Program in future fiscal years if the most current independent cost estimate for the major system is accurate and additional appropriations are required in future fiscal years to ensure the continued development or procurement of the major system, including the consequences of such funding shortfalls on the major system and all other programs of the National Foreign Intelligence Program; and
(d)
Inclusion of estimates in budget justification materials
The budget justification materials submitted to Congress in support of the budget of the President shall include the most current independent cost estimate under this section for each major system for which appropriations are requested in such budget for any fiscal year.
(e)
Definitions
In this section:
(1)
The term “budget of the President” means the budget of the President for a fiscal year as submitted to Congress under section
1105
(a) of title
31.
(2)
The term “independent cost estimate” means a pragmatic and neutral analysis, assessment, and quantification of all costs and risks associated with the acquisition of a major system, which shall be based on programmatic and technical specifications provided by the office within the element of the intelligence community with primary responsibility for the development, procurement, or operation of the major system.
(3)
The term “major system” means any significant program of an element of the intelligence community with projected total development and procurement costs exceeding $500,000,000 (in current fiscal year dollars), which costs shall include all end-to-end program costs, including costs associated with the development and procurement of the program and any other costs associated with the development and procurement of systems required to support or utilize the program.