§ 1962d-5b. Written agreement requirement for water resources projects
(a)
Cooperation of non-Federal interest
(1)
In general
After December 31, 1970, the construction of any water resources project, or an acceptable separable element thereof, by the Secretary of the Army, acting through the Chief of Engineers, or by a non-Federal interest where such interest will be reimbursed for such construction under any provision of law, shall not be commenced until each non-Federal interest has entered into a written partnership agreement with the Secretary (or, where appropriate, the district engineer for the district in which the project will be carried out) under which each party agrees to carry out its responsibilities and requirements for implementation or construction of the project or the appropriate element of the project, as the case may be; except that no such agreement shall be required if the Secretary determines that the administrative costs associated with negotiating, executing, or administering the agreement would exceed the amount of the contribution required from the non-Federal interest and are less than $25,000.
(2)
Liquidated damages
A partnership agreement described in paragraph (1) may include a provision for liquidated damages in the event of a failure of one or more parties to perform.
(3)
Obligation of future appropriations
In any partnership agreement described in paragraph (1) and entered into by a State, or a body politic of the State which derives its powers from the State constitution, or a governmental entity created by the State legislature, the agreement may reflect that it does not obligate future appropriations for such performance and payment when obligating future appropriations would be inconsistent with constitutional or statutory limitations of the State or a political subdivision of the State.
(4)
Credit for in-kind contributions
(A)
In general
A partnership agreement described in paragraph (1) may provide with respect to a project that the Secretary shall credit toward the non-Federal share of the cost of the project, including a project implemented without specific authorization in law, the value of in-kind contributions made by the non-Federal interest, including—
(i)
the costs of planning (including data collection), design, management, mitigation, construction, and construction services that are provided by the non-Federal interest for implementation of the project;
(B)
Condition
The Secretary may credit an in-kind contribution under subparagraph (A) only if the Secretary determines that the material or service provided as an in-kind contribution is integral to the project.
(C)
Work performed before partnership agreement
In any case in which the non-Federal interest is to receive credit under subparagraph (A)(ii) for the cost of work carried out by the non-Federal interest and such work has not been carried out as of November 8, 2007, the Secretary and the non-Federal interest shall enter into an agreement under which the non-Federal interest shall carry out such work, and only work carried out following the execution of the agreement shall be eligible for credit.
(D)
Limitations
Credit authorized under this paragraph for a project—
(ii)
shall not alter any other requirement that a non-Federal interest provide lands, easements, relocations, rights-of-way, or areas for disposal of dredged material for the project;
(E)
Applicability
(i)
In general
This paragraph shall apply to water resources projects authorized after November 16, 1986, including projects initiated after November 16, 1986, without specific authorization in law.
(ii)
Limitation
In any case in which a specific provision of law provides for a non-Federal interest to receive credit toward the non-Federal share of the cost of a study for, or construction or operation and maintenance of, a water resources project, the specific provision of law shall apply instead of this paragraph.
(b)
Definition of non-Federal interest
The term “non-Federal interest” means—
that has full authority and capability to perform the terms of its agreement and to pay damages, if necessary, in the event of failure to perform.
(c)
Enforcement; jurisdiction
Every agreement entered into pursuant to this section shall be enforcible in the appropriate district court of the United States.
(d)
Nonperformance of terms of agreement by non-Federal interest; notice; reasonable opportunity for performance; performance by Chief of Engineers
After commencement of construction of a project, the Chief of Engineers may undertake performance of those items of cooperation necessary to the functioning of the project for its purposes, if he has first notified the non-Federal interest of its failure to perform the terms of its agreement and has given such interest a reasonable time after such notification to so perform.
(e)
Delegation of authority
Not later than June 30, 2008, the Secretary shall issue policies and guidelines for partnership agreements that delegate to the district engineers, at a minimum—
(1)
the authority to approve any policy in a partnership agreement that has appeared in an agreement previously approved by the Secretary;
(2)
the authority to approve any policy in a partnership agreement the specific terms of which are dictated by law or by a final feasibility study, final environmental impact statement, or other final decision document for a water resources project;
(3)
the authority to approve any partnership agreement that complies with the policies and guidelines issued by the Secretary; and
(4)
the authority to sign any partnership agreement for any water resources project unless, within 30 days of the date of authorization of the project, the Secretary notifies the district engineer in which the project will be carried out that the Secretary wishes to retain the prerogative to sign the partnership agreement for that project.
(f)
Report to Congress
Not later than 2 years after November 8, 2007, and every year thereafter, the Secretary shall submit to Congress a report detailing the following:
(g)
Public availability
Not later than 120 days after November 8, 2007, the Chief of Engineers shall—