§ 418a. Rights in technical data

(a) Regulations; legitimate proprietary interest of United States
The legitimate proprietary interest of the United States and of a contractor in technical or other data shall be defined in regulations prescribed as part of the single system of Government-wide procurement regulations as defined in section 403 (4) [1] of this title. Such regulations may not impair any right of the United States or of any contractor with respect to patents or copyrights or any other right in technical data otherwise established by law. Such regulations shall provide, with respect to executive agencies that are subject to the provisions of title III of the Federal Property and Administrative Services Act of 1949 [41 U.S.C. 251 et seq.], that the United States may not require persons who have developed products or processes offered or to be offered for sale to the public as a condition for the procurement of such products or processes by the United States, to provide to the United States technical data relating to the design, development, or manufacture of such products or processes (except for such data as may be necessary for the United States to operate and maintain the product or use the process if obtained by the United States as an element of performance under the contract).
(b) Unlimited rights; technical data; developed with Federal funds; unrestricted, royalty-free right to use; rights under law
(1) Except as otherwise expressly provided by Federal statute, the regulations prescribed pursuant to subsection (a) of this section shall provide, with respect to executive agencies that are subject to the provisions of title III of the Federal Property and Administrative Services Act of 1949 [41 U.S.C. 251 et seq.], that the United States shall have unlimited rights in technical data developed exclusively with Federal funds if delivery of such data—
(A) was required as an element of performance under a contract; and
(B) is needed to ensure the competitive acquisition of supplies or services that will be required in substantial quantities in the future.
(2) Except as otherwise expressly provided by Federal statute, the regulations prescribed pursuant to subsection (a) of this section shall provide, with respect to executive agencies that are subject to the provisions of title III of the Federal Property and Administrative Services Act of 1949 [41 U.S.C. 251 et seq.], that the United States (and each agency thereof) shall have an unrestricted, royalty-free right to use, or to have its contractors use, for governmental purposes (excluding publication outside the Government) technical data developed exclusively with Federal funds.
(3) The requirements of paragraphs (1) and (2) shall be in addition to and not in lieu of any other rights that the United States may have pursuant to law.
(c) Factors; regulations
The following factors shall be considered in prescribing regulations pursuant to subsection (a) of this section:
(1) Whether the item or process to which the technical data pertains was developed—
(A) exclusively with Federal funds;
(B) exclusively at private expense; or
(C) in part with Federal funds and in part at private expense.
(2) The statement of congressional policy and objectives in section 200 of title 35, the statement of purposes in section 2(b) of the Small Business Innovation Development Act of 1982 (Public Law 97–219; 15 U.S.C. 638 note ), and the declaration of policy in section 631 of title 15.
(3) The interest of the United States in increasing competition and lowering costs by developing and locating alternative sources of supply and manufacture.
(d) Provisions; contracts; regulations
Regulations prescribed under subsection (a) of this section shall require that a contract for property or services entered into by an executive agency contain appropriate provisions relating to technical data, including provisions—
(1) defining the respective rights of the United States and the contractor or subcontractor (at any tier) regarding any technical data to be delivered under the contract;
(2) specifying the technical data, if any, to be delivered under the contract and delivery schedules for such delivery;
(3) establishing or referencing procedures for determining the acceptability of technical data to be delivered under the contract;
(4) establishing separate contract line items for the technical data, if any, to be delivered under the contract;
(5) to the maximum practicable extent, identifying, in advance of delivery, technical data which is to be delivered with restrictions on the right of the United States to use such data;
(6) requiring the contractor to revise any technical data delivered under the contract to reflect engineering design changes made during the performance of the contract and affecting the form, fit, and function of the items specified in the contract and to deliver such revised technical data to an agency within a time specified in the contract;
(7) requiring the contractor to furnish written assurance at the time the technical data is delivered or is made available that the technical data is complete and accurate and satisfies the requirements of the contract concerning technical data;
(8) establishing remedies to be available to the United States when technical data required to be delivered or made available under the contract is found to be incomplete or inadequate or to not satisfy the requirements of the contract concerning technical data; and
(9) authorizing the head of the agency to withhold payments under the contract (or exercise such other remedies as the head of the agency considers appropriate) during any period if the contractor does not meet the requirements of the contract pertaining to the delivery of technical data.


[1] See References in Text note below.