§ 2331. Use of continuing contracts for construction of certain projects
(a)
In general
Notwithstanding any other provision of law, the Secretary shall not implement a fully allocated funding policy with respect to a water resource project if initiation of construction has occurred but sufficient funds are not available to complete the project.
(b)
Continuing contracts
The Secretary shall enter into a continuing contract for a project described in subsection (a) of this section.
(c)
Initiation of construction clarified
For the purposes of this section, initiation of construction for a project occurs on the date of enactment of an Act that appropriates funds for the project from 1 of the following appropriation accounts: