§ 824j. Wheeling authority

(a) Transmission service by any electric utility; notice, hearing and findings by Commission
Any electric utility, Federal power marketing agency, or any other person generating electric energy for sale for resale, may apply to the Commission for an order under this subsection requiring a transmitting utility to provide transmission services (including any enlargement of transmission capacity necessary to provide such services) to the applicant. Upon receipt of such application, after public notice and notice to each affected State regulatory authority, each affected electric utility, and each affected Federal power marketing agency, and after affording an opportunity for an evidentiary hearing, the Commission may issue such order if it finds that such order meets the requirements of section 824k of this title, and would otherwise be in the public interest. No order may be issued under this subsection unless the applicant has made a request for transmission services to the transmitting utility that would be the subject of such order at least 60 days prior to its filing of an application for such order.
(b) Reliability of electric service
No order may be issued under this section or section 824i of this title if, after giving consideration to consistently applied regional or national reliability standards, guidelines, or criteria, the Commission finds that such order would unreasonably impair the continued reliability of electric systems affected by the order.
(c) Replacement of electric energy
No order may be issued under subsection (a) or (b) of this section which requires the transmitting utility subject to the order to transmit, during any period, an amount of electric energy which replaces any amount of electric energy—
(1) required to be provided to such applicant pursuant to a contract during such period, or
(2) currently provided to the applicant by the utility subject to the order pursuant to a rate schedule on file during such period with the Commission: Provided, That nothing in this subparagraph shall prevent an application for an order hereunder to be filed prior to termination or modification of an existing rate schedule: Provided, That such order shall not become effective until termination of such rate schedule or the modification becomes effective.
(d) Termination or modification of order; notice, hearing and findings of Commission; contents of order; inclusion in order of terms and conditions agreed upon by parties
(1) Any transmitting utility ordered under subsection (a) or (b) of this section to provide transmission services may apply to the Commission for an order permitting such transmitting utility to cease providing all, or any portion of, such services. After public notice, notice to each affected State regulatory authority, each affected Federal power marketing agency, each affected transmitting utility, and each affected electric utility, and after an opportunity for an evidentiary hearing, the Commission shall issue an order terminating or modifying the order issued under subsection (a) or (b) of this section, if the transmitting utility providing such transmission services has demonstrated, and the Commission has found, that—
(A) due to changed circumstances, the requirements applicable, under this section and section 824k of this title, to the issuance of an order under subsection (a) or (b) of this section are no longer met, or [1]
(B) any transmission capacity of the utility providing transmission services under such order which was, at the time such order was issued, in excess of the capacity necessary to serve its own customers is no longer in excess of the capacity necessary for such purposes, or
(C) the ordered transmission services require enlargement of transmission capacity and the transmitting utility subject to the order has failed, after making a good faith effort, to obtain the necessary approvals or property rights under applicable Federal, State, and local laws.
No order shall be issued under this subsection pursuant to a finding under subparagraph (A) unless the Commission finds that such order is in the public interest.
(2) Any order issued under this subsection terminating or modifying an order issued under subsection (a) or (b) of this section shall—
(A) provide for any appropriate compensation, and
(B) provide the affected electric utilities adequate opportunity and time to—
(i) make suitable alternative arrangements for any transmission services terminated or modified, and
(ii) insure that the interests of ratepayers of such utilities are adequately protected.
(3) No order may be issued under this subsection terminating or modifying any order issued under subsection (a) or (b) of this section if the order under subsection (a) or (b) of this section includes terms and conditions agreed upon by the parties which—
(A) fix a period during which transmission services are to be provided under the order under subsection (a) or (b) of this section, or
(B) otherwise provide procedures or methods for terminating or modifying such order (including, if appropriate, the return of the transmission capacity when necessary to take into account an increase, after the issuance of such order, in the needs of the transmitting utility subject to such order for transmission capacity).
(e) “Facilities” defined
As used in this section, the term “facilities” means only facilities used for the generation or transmission of electric energy.


[1] So in original. The word “or” probably should not appear.