§ 720h. Clarification of ANGTA status and authorities
(a)
Savings clause
Nothing in this chapter affects—
(b)
Clarification of authority to amend terms and conditions to meet current project requirements
Any Federal agency responsible for granting or issuing any certificate, permit, right-of-way, lease, or other authorization under section 9 of the Alaska Natural Gas Transportation Act of 1976 (15 U.S.C. 719g) may add to, amend, or rescind any term or condition included in the certificate, permit, right-of-way, lease, or other authorization to meet current project requirements (including the physical design, facilities, and tariff specifications), if the addition, amendment, or rescission—
(c)
Updated environmental reviews
The Secretary shall require the sponsor of the Alaska natural gas transportation system to submit such updated environmental data, reports, permits, and impact analyses as the Secretary determines are necessary to develop detailed terms, conditions, and compliance plans required by section 5 of the President’s decision.