§ 2433. Unit cost reports
(a)
In this section:
(1)
Except as provided in section
2430a
(d) of this title, the terms “program acquisition unit cost”, “procurement unit cost”, and “major contract” have the same meanings as provided in section
2432
(a) of this title.
(2)
The term “Baseline Estimate”, with respect to a unit cost report that is submitted under this section to the service acquisition executive designated by the Secretary concerned on a major defense acquisition program or designated major subprogram, means the cost estimate included in the baseline description for the program or subprogram under section
2435 of this title.
(3)
The term “procurement program” means a program for which funds for procurement are authorized to be appropriated in a fiscal year.
(4)
The term “significant cost growth threshold” means the following:
(A)
In the case of a major defense acquisition program or designated major defense subprogram, a percentage increase in the program acquisition unit cost for the program or subprogram of—
(B)
In the case of a major defense acquisition program or designated major defense subprogram that is a procurement program, a percentage increase in the procurement unit cost for the program or subprogram of—
(5)
The term “critical cost growth threshold” means the following:
(A)
In the case of a major defense acquisition program or designated major defense subprogram, a percentage increase in the program acquisition unit cost for the program or subprogram of—
(B)
In the case of a major defense acquisition program or designated major defense subprogram that is a procurement program, a percentage increase in the procurement unit cost for the program or subprogram of—
(b)
The program manager for a major defense acquisition program (other than a program not required to be included in the Selected Acquisition Report for that quarter under section
2432
(b)(3) of this title) shall, on a quarterly basis, submit to the service acquisition executive designated by the Secretary concerned a written report on the unit costs of the program (or of each designated major subprogram under the program). Each report shall be submitted not more than 30 calendar days after the end of that quarter. The program manager shall include in each such unit cost report the following information with respect to the program (as of the last day of the quarter for which the report is made):
(1)
The program acquisition unit cost for the program (or for each designated major subprogram under the program).
(2)
In the case of a procurement program, the procurement unit cost for the program (or for each designated major subprogram under the program).
(3)
Any cost variance or schedule variance in a major contract under the program since the contract was entered into.
(4)
Any changes from program schedule milestones or program performances reflected in the baseline description established under section
2435 of this title that are known, expected, or anticipated by the program manager.
(5)
Any significant changes in the total program cost for development and procurement of the software component of the program or subprogram, schedule milestones for the software component of the program or subprogram, or expected performance for the software component of the program or subprogram that are known, expected, or anticipated by the program manager.
(c)
If the program manager of a major defense acquisition program for which a unit cost report has previously been submitted under subsection (b) determines at any time during a quarter that there is reasonable cause to believe that the program acquisition unit cost for the program (or for a designated major subprogram under the program) or the procurement unit cost for the program (or for such a subprogram), as applicable, has increased by a percentage equal to or greater than the significant cost growth threshold; and if a unit cost report indicating an increase of such percentage or more has not previously been submitted to the service acquisition executive designated by the Secretary concerned, then the program manager shall immediately submit to such service acquisition executive a unit cost report containing the information, determined as of the date of the report, required under subsection (b).
(d)
(1)
When a unit cost report is submitted to the service acquisition executive designated by the Secretary concerned under this section with respect to a major defense acquisition program or any designated major subprogram under the program, the service acquisition executive shall determine whether the current program acquisition unit cost for the program or subprogram has increased by a percentage equal to or greater than the significant cost growth threshold, or the critical cost growth threshold, for the program or subprogram.
(2)
When a unit cost report is submitted to the service acquisition executive designated by the Secretary concerned under this section with respect to a major defense acquisition program or any designated major subprogram under the program that is a procurement program, the service acquisition executive, in addition to the determination under paragraph (1), shall determine whether the procurement unit cost for the program or subprogram has increased by a percentage equal to or greater than the significant cost growth threshold, or the critical cost growth threshold, for the program or subprogram.
(3)
If, based upon the service acquisition executive’s determination, the Secretary concerned determines that the current program acquisition unit cost has increased by a percentage equal to or greater than the significant cost growth threshold or critical cost growth threshold or that the procurement unit cost has increased by a percentage equal to or greater than the significant cost growth threshold or critical cost growth threshold, the Secretary shall notify Congress in writing of such determination and of the increase with respect to the program or subprogram concerned. In the case of a determination based on a quarterly report submitted in accordance with subsection (b), the Secretary shall submit the notification to Congress within 45 days after the end of the quarter. In the case of a determination based on a report submitted in accordance with subsection (c), the Secretary shall submit the notification to Congress within 45 days after the date of that report. The Secretary shall include in the notification the date on which the determination was made.
(e)
(1)
(A)
Except as provided in subparagraph (B), whenever the Secretary concerned determines under subsection (d) that the program acquisition unit cost or the procurement unit cost of a major defense acquisition program or designated major subprogram has increased by a percentage equal to or greater than the significant cost growth threshold for the program or subprogram, a Selected Acquisition Report shall be submitted to Congress for the first fiscal-year quarter ending on or after the date of the determination or for the fiscal-year quarter which immediately precedes the first fiscal-year quarter ending on or after that date. The report shall include the information described in section
2432
(e) of this title and shall be submitted in accordance with section
2432
(f) of this title.
(B)
Whenever the Secretary makes a determination referred to in subparagraph (A) in the case of a major defense acquisition program or designated major subprogram during the second quarter of a fiscal year and before the date on which the President transmits the budget for the following fiscal year to Congress pursuant to section
1105 of title
31, the Secretary is not required to file a Selected Acquisition Report under subparagraph (A) but shall include the information described in subsection (g) regarding that program or subprogram in the comprehensive annual Selected Acquisition Report submitted in that quarter.
(2)
If the program acquisition unit cost or procurement unit cost of a major defense acquisition program or designated major subprogram (as determined by the Secretary under subsection (d)) increases by a percentage equal to or greater than the critical cost growth threshold for the program or subprogram, the Secretary of Defense shall take actions consistent with the requirements of section
2433a of this title.
(3)
If a determination of an increase by a percentage equal to or greater than the significant cost growth threshold is made by the Secretary under subsection (d) and a Selected Acquisition Report containing the information described in subsection (g) is not submitted to Congress under paragraph (1), or if a determination of an increase by a percentage equal to or greater than the critical cost growth threshold is made by the Secretary under subsection (d) and the certification of the Secretary of Defense is not submitted to Congress under paragraph (2), funds appropriated for military construction, for research, development, test, and evaluation, and for procurement may not be obligated for a major contract under the program. The prohibition on the obligation of funds for a major defense acquisition program shall cease to apply at the end of a period of 30 days of continuous session of Congress (as determined under section
7307
(b)(2) of this title) beginning on the date—
(A)
on which Congress receives the Selected Acquisition Report under paragraph (1) or (2)(B) with respect to that program, in the case of a determination of an increase by a percentage equal to or greater than the significant cost growth threshold (as determined in subsection (d)); or
(B)
on which Congress has received both the Selected Acquisition Report under paragraph (1) or (2)(B) and the certification of the Secretary of Defense under paragraph (2)(A) with respect to that program, in the case of an increase by a percentage equal to or greater than the critical cost growth threshold (as determined under subsection (d)).
(f)
Any determination of a percentage increase under this section shall be stated in terms of constant base year dollars (as described in section
2430 of this title).
(g)
(1)
Except as provided in paragraph (2), each report under subsection (e) with respect to a major defense acquisition program shall include the following:
(D)
The estimate of the program acquisition cost for the program (and for each designated major subprogram under the program) as shown in the Selected Acquisition Report in which the program or subprogram was first included, expressed in constant base-year dollars and in current dollars.
(E)
The current program acquisition cost for the program (and for each designated major subprogram under the program) in constant base-year dollars and in current dollars.
(F)
A statement of the reasons for any increase in program acquisition unit cost or procurement unit cost for the program (or for any designated major subprogram under the program).
(G)
The completion status of the program and each designated major subprogram under the program
(i)
expressed as the percentage that the number of years for which funds have been appropriated for the program or subprogram is of the number of years for which it is planned that funds will be appropriated for the program or subprogram, and
(ii)
expressed as the percentage that the amount of funds that have been appropriated for the program or subprogram is of the total amount of funds which it is planned will be appropriated for the program or subprogram.
(H)
The fiscal year in which information on the program and each designated major subprogram under the program was first included in a Selected Acquisition Report (referred to in this paragraph as the “base year”) and the date of that Selected Acquisition Report in which information on the program or subprogram was first included.
(I)
The type of the Baseline Estimate that was included in the baseline description under section
2435 of this title and the date of the Baseline Estimate.
(J)
The current change and the total change, in dollars and expressed as a percentage, in the program acquisition unit cost for the program (or for each designated major subprogram under the program), stated both in constant base-year dollars and in current dollars.
(K)
The current change and the total change, in dollars and expressed as a percentage, in the procurement unit cost for the program (or for each designated major subprogram under the program), stated both in constant base-year dollars and in current dollars and the procurement unit cost for the program (or for each designated major subprogram under the program) for the succeeding fiscal year expressed in constant base-year dollars and in current year dollars.
(L)
The quantity of end items to be acquired under the program and the current change and total change, if any, in that quantity.
(M)
The identities of the military and civilian officers responsible for program management and cost control of the program.
(O)
Any changes made in the performance or schedule milestones of the program and the extent to which such changes have contributed to the increase in program acquisition unit cost or procurement unit cost for the program (or for any designated major subprogram under the program).
(P)
The following contract performance assessment information with respect to each major contract under the program or subprogram:
(iv)
Any current change and the total change, in dollars and expressed as a percentage, in the contract cost.
(vi)
A narrative providing a summary explanation of the most significant occurrences, including cost and schedule variances under major contracts of the program and any designated major subprogram under the program, contributing to the changes identified and a discussion of the effect these occurrences will have on future program costs and the program schedule.
(2)
If a program acquisition unit cost increase or a procurement unit cost increase for a major defense acquisition program or designated major subprogram that results in a report under this subsection is due to termination or cancellation of the entire program or subprogram, only the information specified in clauses (A) through (F) of paragraph (1) and the percentage change in program acquisition unit cost or procurement unit cost that resulted in the report need be included in the report. The certification of the Secretary of Defense under subsection (e) is not required to be submitted for termination or cancellation of a program or subprogram.
(h)
Reporting under this section shall not apply if a program has received a limited reporting waiver under section
2432
(h) of this title.