§24-2-11 Requirements for certificate of public convenience and necessity.
§24-2-11. Requirements for certificate of public convenience and necessity.
(a) A public utility, person or corporation may not begin the construction of any plant, equipment, property or facility for furnishing to the public any of the services enumerated in section one, article two of this chapter, nor apply for, nor obtain any franchise, license or permit from any municipality or other governmental agency, except ordinary extensions of existing systems in the usual course of business, unless and until it shall obtain from the Public Service Commission a certificate of public convenience and necessity authorizing such construction franchise, license or permit.
(b) Upon the filing of any application for the certificate, and after hearing, the commission may, in its discretion, issue or refuse to issue, or issue in part and refuse in part, the certificate of convenience and necessity: Provided, That the commission, after it gives proper notice and if no substantial protest is received within thirty days after the notice is given, may waive formal hearing on the application. Notice shall be given by publication which shall state that a formal hearing may be waived in the absence of substantial protest, made within thirty days, to the application. The notice shall be published as a Class I legal advertisement in compliance with the provisions of article three, chapter fifty-nine of this code. The publication area shall be the proposed area of operation.
(c) Any public utility, person or corporation subject to the provisions of this section shall give the commission at least thirty days' notice of the filing of any the application for a certificate of public convenience and necessity under this section: Provided, That the commission may modify or waive the thirty-day notice requirement and shall waive the thirty-day notice requirement for projects approved by the Infrastructure and Jobs Development Council.
(d) The commission shall render its final decision on any application filed under the provisions of this section or section eleven-a of this article within two hundred seventy days of the filing of the application and within ninety days after final submission of any such application for decision following a hearing: Provided, That if the application is for authority to construct a water and sewer project and the projected total cost is less than $10 million, the Commission shall render its final decision within two hundred twenty-five days of the filing of the application.
(e) The commission shall render its final decision on any application filed under the provisions of this section that has received the approval of the Infrastructure and Jobs Development Council pursuant to article fifteen-a, chapter thirty-one of this code within one hundred eighty days after filing of the application: Provided, That if a substantial protest is received within thirty days after the notice is provided pursuant to subsection (b) of this section, the commission shall render its final decision within two hundred seventy days or two hundred twenty-five days of the filing of the application, whichever is applicable as determined in subsection (d).
(f) If the projected total cost of a project which is the
subject of an application filed pursuant to this section or section eleven-a of this article is greater than $50 million, the commission shall render its final decision on any such application filed under the provisions of this section or section eleven-a of this article within four hundred days of the filing of the application and within ninety days after final submission of any such application for decision after a hearing.
(g) If a decision is not rendered within the, time-frames established in this section, the commission shall issue a certificate of convenience and necessity as applied for in the application.
(h) The commission shall prescribe rules as it may deem proper for the enforcement of the provisions of this section; and, in establishing that public convenience and necessity do exist, the burden of proof shall be upon the applicant.
(i) Pursuant to the requirements of this section, the commission may issue a certificate of public convenience and necessity to any intrastate pipeline, interstate pipeline or local distribution company for the transportation in intrastate commerce of natural gas used by any person for one or more uses, as defined by rule, by the commission in the case of:
(1) Natural gas sold by a producer, pipeline or other seller to the person; or
(2) Natural gas produced by the person.
(j) A public utility, including a public service district, which has received a certificate of public convenience and necessity after July 8, 2005, from the commission and has been approved by the Infrastructure and Jobs Development Council, is not required to, and cannot be compelled to, reopen the proceeding if the cost of the project changes but the change does not affect the rates established for the project.
(k) Any public utility, person or corporation proposing any electric power project that requires a certificate under this section is not required to obtain such certificate before applying for or obtaining any franchise, license or permit from any municipality or other governmental agency.