81.104.115 - Rail fixed guideway system -- Safety program plan and security and emergency preparedness plan.
Rail fixed guideway system — Safety program plan and security and emergency preparedness plan.
(1) The department may collect and review the system safety program plan and the system security and emergency preparedness plan prepared by each owner or operator of a rail fixed guideway system. In carrying out this function, the department may adopt rules specifying the elements and standard to be contained in a system safety program plan and a system security and emergency preparedness plan, and the content of any investigation report, corrective action plan, and accompanying implementation schedule resulting from a reportable accident, unacceptable hazardous condition, or security breach. These rules may include due dates for the department's timely receipt of and response to required documents.
(2) The system security and emergency preparedness plan as described in subsection (1)(d) of RCW 35.21.228, 35A.21.300, 36.01.210, 36.57.120, 36.57A.170, and 81.112.180 is exempt from public disclosure under chapter 42.56 RCW by the department when collected from the owners and operators of fixed railway systems. However, the system safety program plan as described in RCW 35.21.228, 35A.21.300, 36.01.210, 36.57.120, 36.57A.170, and 81.112.180 is not exempt from public disclosure.
(3) The department shall audit each system safety program plan and each system security and emergency preparedness plan at least once every three years. The department may contract with other persons or entities for the performance of duties required by this subsection. The department shall provide at least thirty days' advance notice to the owner or operator of a rail fixed guideway system before commencing the audit. The owner or operator of each rail fixed guideway system shall reimburse the reasonable expenses of the department in carrying out its responsibilities of this subsection within ninety days after receipt of an invoice. The department shall notify the owner or operator of the estimated expenses at least six months in advance of when the department audits the system.
(4) In the event of a reportable accident, unacceptable hazardous condition, or security breach, the department shall review the investigation report, corrective action plan, and accompanying implementation schedule, submitted by the owner or operator of the rail fixed guideway system to ensure that it meets the goal of preventing and mitigating a recurrence of the reportable accident, unacceptable hazardous condition, or security breach.
(a) The department may, at its option, perform a separate, independent investigation of a reportable accident, unacceptable hazardous condition, or security breach. The department may contract with other persons or entities for the performance of duties required by this subsection.
(b) If the department does not concur with the investigation report, corrective action plan, and accompanying implementation schedule, submitted by the owner or operator, the department shall notify that owner or operator in writing within forty-five days of its receipt of the complete investigation report, corrective action plan, and accompanying implementation schedule.
(5) The secretary may adopt rules to implement this section and RCW 35.21.228, 35A.21.300, 36.01.210, 36.57.120, 36.57A.170, and 81.112.180, including rules establishing procedures and timelines for owners and operators of rail fixed guideway systems to comply with RCW 35.21.228, 35A.21.300, 36.01.210, 36.57.120, 36.57A.170, and 81.112.180 and the rules adopted under this section. If noncompliance by an owner or operator of a rail fixed guideway system results in the loss of federal funds to the state of Washington or a political subdivision of the state, the owner or operator is liable to the affected entity or entities for the amount of the lost funds.
(6) The department may impose sanctions upon owners and operators of rail fixed guideway systems, but only for failure to meet reasonable deadlines for submission of required reports and audits. The department is expressly prohibited from imposing sanctions for any other purposes, including, but not limited to, differences in format or content of required reports and audits.
(7) The department and its employees have no liability arising from the adoption of rules; the review of or concurrence in a system safety program plan and a system security and emergency preparedness plan; the separate, independent investigation of a reportable accident, unacceptable hazardous condition, or security breach; and the review of or concurrence in a corrective action plan for a reportable accident, unacceptable hazardous condition, or security breach.
(8) The department shall set by rule an annual fee for owners and operators of rail fixed guideway systems to defray the department's direct costs associated only with the system safety program plans, system security and emergency preparedness plans, and incident investigations, as described in this section, and the fee shall not be a flat fee but shall be imposed on each owner and operator in proportion to the effort expended by the department in relation to individual plans. The department shall establish by rule the manner and timing of the collection of the fee.
[2007 c 422 § 7; 2005 c 274 § 359; 2001 c 127 § 1; 1999 c 202 § 7.]
Notes: Part headings not law -- Effective date -- 2005 c 274: See RCW 42.56.901 and 42.56.902.
Effective date -- 1999 c 202: See note following RCW 35.21.228.