(1) (a) A land use authority shall grant or deny a public utility's land use permit within 60days after filing in accordance with the provisions of Title 10, Chapter 9a, Municipal Land Use,Development, and Management Act, and Title 17, Chapter 27a, County Land Use, Development,and Management Act.
(b) The Utility Facility Review Board may review a land use authority's land use permitdecision in accordance with Title 54, Chapter 14, Part 3, Utility Facility Review Board.
(2) Notwithstanding Subsection (1), if a public utility does not satisfy the notice of intentrequirements in accordance with Section 54-18-301 and public workshop requirements inaccordance with Section 54-18-302, a land use authority may withhold a decision on a publicutility's land use permit until the public utility satisfies the notification and public workshoprequirements.