38-1-6 - Priority over claims of creditors of original contractor or subcontractor.
38-1-6. Priority over claims of creditors of original contractor or subcontractor.
No attachment, garnishment or levy under an execution upon any money due to anoriginal contractor from the owner of any property subject to lien under this chapter shall be validas against any lien of a subcontractor or materialman, and no such attachment, garnishment orlevy upon any money due to a subcontractor or materialman from the contractor shall be valid asagainst any lien of a laborer employed by the day or piece.
No Change Since 1953