66-11-121 - Insurance proceeds subject to liens.
66-11-121. Insurance proceeds subject to liens.
(a) The proceeds of any insurance that by the terms of the policy are payable to the owner of real property improved, and are actually received by or are to be received by the owner because of the destruction or removal by fire or other casualty of an improvement on which lienors have performed labor, or for which they have furnished materials, services, equipment, or machinery shall, after the owner has been reimbursed from the proceeds for premiums paid for the insurance by the owner, if any, be subject to liens provided by this chapter to the same extent and in the same order of priority as the real property would have been had the improvement not been so destroyed or removed.
(b) The proceeds of any insurance that by the terms of the policy are payable to a prime contractor or remote contractor, and are received or to be received by the prime contractor or remote contractor, shall, after the prime contractor or remote contractor has been reimbursed from the proceeds for premiums paid for the insurance by the prime contractor or remote contractor, if any, be liable for the payment for labor or materials, services, equipment, or machinery furnished and for which the prime contractor or remote contractor is liable in the same manner and under the same conditions as payments to the prime contractor or remote contractor under the contract would have been had the improvements not been so destroyed or removed.
[Code 1932, § 7934; T.C.A. (orig. ed.), § 64-1121; Acts 2007, ch. 189, § 20.]