13-18-120 - Certification of approvals Effect.
13-18-120. Certification of approvals Effect.
(a) If the joint review team has been notified by the agencies with authority to grant such approvals or perform such actions, or by a reviewing court, that all agency actions and approvals on the project decision schedules relating to a priority energy project:
(1) Have been granted;
(2) Have been performed; or
(3) Are not necessary;
and if judicial review of such actions or approvals is completed, then the team shall certify the same. Such certification shall indicate any conditions and the expiration date of any approvals that have been granted to the project.
(b) A certificate issued by the team under subsection (a) shall constitute conclusive evidence in any judicial or executive proceeding that all actions and approvals necessary to the completion and initial operation of the project have been granted for the duration and subject to the conditions specified on the certificate.
[Acts 1981, ch. 131, § 20.]