Section 49-34A-16 - Delay in effectuation of suspended rate schedule pending disposition ofpreviously filed changes--Time--Violation as petty offense--Separateoffenses.
49-34A-16. Delay in effectuation of suspended rate schedule pending disposition of previously filed changes--Time--Violation as petty offense--Separate offenses. No public utility may put a suspended rate schedule into effect until at least forty-five days after the Public Utilities Commission has made a determination concerning any previously filed change of the rate schedule. An intentional violation of this section is a petty offense. After the first judgment, each day's violation is a separate offense.
Source: SL 1975, ch 283, § 9; SL 1976, ch 296, § 16; SL 1983, ch 15, § 142.