Section 49-7A-5 - Notification of proposed excavation.

49-7A-5. Notification of proposed excavation. No excavator may begin any excavation without first notifying the one-call notification center of the proposed excavation. The excavator shall give notice by telephone or by other methods approved by the board pursuant to rules promulgated pursuant to chapter 1-26 to the one-call notification center at least forty-eight hours prior to the commencement of the excavation, excluding Saturdays, Sundays, and legal holidays of the state. The board may promulgate rules to reduce the forty-eight-hour interval for emergency or subsequent inquiries to the original locate request and may lengthen the forty-eight-hour interval for nonexcavation requests.

Source: SL 1993, ch 346, § 6; SL 1994, ch 354, § 4; SL 1997, ch 263, § 2; SL 2002, ch 211, § 3; SL 2007, ch 264, § 2.