Section 34-44-6 - Responsibility of asbestos contractor for handling and delivery of friable asbestosmaterial--Penalty for violation.
34-44-6. Responsibility of asbestos contractor for handling and delivery of friable asbestos material--Penalty for violation. The asbestos contractor carrying out an asbestos project is responsible for the safe and proper handling and delivery of waste that includes friable asbestos material to a landfill authorized to receive such waste. A violation of this section is a Class 1 misdemeanor.
In addition, any person who violates this section is subject to a civil penalty not to exceed one thousand dollars per day of violation.
Source: SL 1988, ch 284, § 5; SL 1990, ch 280, § 3; SL 1993, ch 254.