§ 143-215.29. Supervision by qualified engineers; reports and modification during work.
§ 143‑215.29. Supervision by qualified engineers; reports and modification during work.
(a) Any project for which the Commission's approval is requiredunder G.S. 143‑215.26, 143‑215.27, and 143‑215.28, and anyproject undertaken pursuant to an order of the Commission issued pursuant tothis section or G.S. 143‑215.32 shall be designed and supervised by anengineer legally qualified in the State of North Carolina.
(b) During the construction, enlargement, repair, alteration orremoval of a dam, the Commission may require such progress reports from thesupervising engineer as it deems necessary.
(c) If during construction, reconstruction, repair, alterationor enlargement of any dam, the Commission finds the work is not being done inaccordance with the provisions of the approval and the approved plans andspecifications, it shall give written notice by registered mail or personalservice to the person who received the approval and to the person in charge ofconstruction at the dam. The notice shall state the particulars in whichcompliance has not been made, and shall order immediate compliance with theterms of the approval, and the approved plans and specifications. TheCommission may order that no further construction work be undertaken until suchcompliance has been effected and approved by the Commission. A failure tocomply with the approval and the approved plans and specifications shall renderthe approval revocable unless compliance is made after notice as provided inthis section. (1967, c. 1068, s. 7;1973, c. 1262, s. 23; 1977, c. 878, s. 5; 1987, c. 827, s. 154.)