11-102 - Liability of utilities for compensation for damages caused by interfering with, or delaying the progress of work under state public construction contr

§ 11-102. Liability  of  utilities for compensation for damages caused  by interfering with, or delaying the progress of work under state public  construction contracts. 1. No utility shall interfere with, or delay the  progress of work under any contract with the state  department,  agency,  division  or  board, for the construction, reconstruction or improvement  of any highway, street, road, railroad grade crossing,  bridge,  tunnel,  underpass,  overpass  or other state contract work, by failing to remove  or relocate its poles, wires,  cables,  conduits,  pipes  or  any  other  facilities  or  structures  within  the  time  schedule  therefor  by an  agreement or under the terms of an  agreement  between  the  department,  agency,  division  or  board  and the utility, or if no time is fixed by  such an agreement or under the terms of such an  agreement,  within  the  time  fixed  by  the  department,  agency,  division or board, by notice  served upon such utility by such state department, agency,  division  or  board.    2.   If  such  notice  is  utilized,  it  shall  describe  the  public  improvement  and  the  geographical  location  thereof,  the   date   of  commencement  and  the  date  of completion, if any, provided for by the  contract, the contractor's name and address, the manner in which and the  extent to which the facilities and structures of the utility obstruct or  prevent  the  contractor  from  progressing  or  performing   the   work  comprehended by the contract, and shall fix the date or time within such  utility  is required to remove or relocate its facilities or structures,  specifying the same, in order to provide the contractor  with  the  site  when  required  by the contractor for progressing or performing the work  pursuant to such state contract. Such notice shall  be  in  writing  and  shall be served upon such utility either personally or by certified mail  at  its  principal  office  or place of business in the county where the  work under such contract is to be performed, or, if  there  be  no  such  principal  office  or  place  of business in such county, at the nearest  principal office or place of business of such utility, outside  of  such  county.  In  the  event  the  utility  to  whom the aforesaid notice was  directed is for any reason unable,  within  the  prescribed  period,  to  remove  or  relocate  said  facilities  or  structures  specified in the  notice, said utility shall immediately advise said  department,  agency,  division or board and the contractor, in writing, of such inability, and  in the same communication so advise said department, agency, division or  board,  and  the contractor of the approximate date that such removal or  relocation of facilities or structures  could  be  effected;  and  shall  further  state  the basis for the inability of said utility to remove or  relocate said facilities or structures within the time specified by  the  notice served thereon by said department, agency, division or board. The  department,  agency,  division or board, after examining and considering  the utility's basis for  establishing  a  different  schedule  for  such  removal or relocation, shall, if such basis is reasonable, establish and  notify  the utility of a revised schedule for completing such removal or  relocation.    3. In cases  where  the  utility  has  been  reimbursed  for  removal,  relocation,   replacement  or  reconstruction  pursuant  to  subdivision  twenty-four-b of section ten of the highway law, a  utility  failing  to  complete  the  removal  or  relocation  of such structures or facilities  within a period of thirty days beyond the time  fixed  therefor  by  the  latest  time schedule established in accordance with this section, shall  be liable and responsible to any such contractor for any damages, direct  or consequential,  sustained  by  any  such  contractor  as  the  result  thereof,  in  an  action  to  be brought by such contractor against such  utility in a court of competent jurisdiction within two years  from  the  time  fixed  for  the  removal  or  relocation  of  such  structures  orfacilities. If an action is commenced against a utility,  as  heretofore  provided,  said  utility  may interpose in its answer in such action any  defense available under the provisions of the  civil  practice  law  and  rules.  The  unreasonableness  of the time schedule imposed by the state  department, agency, division or board shall be an  absolute  defense  by  the  utility  to  any  such  action  by  the contractor. If, in any such  action, the utility is found to owe nothing to the contractor, or if  an  offer  of settlement is made by the utility which is not accepted by the  contractor and the resulting verdict against the utility  is  less  than  the offer of settlement, then in either such event the total cost of the  utility  of  litigation,  including reasonable attorney's fees, shall be  paid to the utility by the contractor.