Section 485-A:17 Terrain Alteration.


   I. Any person proposing to dredge, excavate, place fill, mine, transport forest products or undertake construction in or on the border of the surface waters of the state, and any person proposing to significantly alter the characteristics of the terrain, in such a manner as to impede the natural runoff or create an unnatural runoff, shall be directly responsible to submit to the department detailed plans concerning such proposal and any additional relevant information requested by the department, at least 30 days prior to undertaking any such activity. The operations shall not be undertaken unless and until the applicant receives a permit from the department. The department shall have full authority to establish the terms and conditions under which any permit issued may be exercised, giving due consideration to the circumstances involved and the purposes of this chapter, and to adopt such rules as are reasonably related to the efficient administration of this section, and the purposes of this chapter. Nothing contained in this paragraph shall be construed to modify or limit the duties and authority conferred upon the department under RSA 482 and RSA 482-A.
   II. The department shall charge a fee for each review of plans, including project inspections, required under this section. The fee shall be based on the extent of contiguous area to be disturbed. Except for RSA 483-B:9, the fee for plans encompassing an area of at least 100,000 square feet but less than 200,000 square feet shall be $1,250. For the purposes of RSA 483-B:9, the fee for plans encompassing an area of at least 50,000 square feet but less than 200,000 square feet shall be $1,250. An additional fee of $500 shall be assessed for each additional area of up to 100,000 square feet to be disturbed. No permit shall be issued by the department until the fee required by this paragraph is paid. All fees required under this paragraph shall be paid when plans are submitted for review and shall be deposited in the terrain alteration fund established in paragraph II-a.
   II-a. There is hereby established the terrain alteration fund into which the fees collected under paragraph II shall be deposited. The fund shall be a separate, nonlapsing fund, continually appropriated to the department for the purpose of paying all costs and salaries associated with the terrain alteration program.
   II-b. In processing an application for permits under RSA 485-A:17:
      (a) Within 50 days of receipt of the application, the department shall request any additional information required to complete its evaluation of the application, together with any written technical comments the department deems necessary. Any request for additional information shall specify that the applicant submit such information as soon as practicable and shall notify the applicant that if all of the requested information is not received within 120 days of the request, the department shall deny the application.
      (b) If the department requests additional information pursuant to subparagraph (a), the department shall, within 30 days of the department's receipt of the information:
         (1) Approve and issue a permit;
         (2) Deny the application, in whole or in part; or
         (3) Extend the time for response for good cause and with the written agreement of the applicant.
      (c) If no request for additional information is made pursuant to subparagraph (b), the department shall, within 50 days of receipt of the application, approve or deny the application, in whole or in part.
      (d) If the department fails to render a decision within the time limits provided in this paragraph, the application shall be deemed to be approved and a permit shall be issued.
      (e) The time limits under this paragraph shall not apply to an application from an applicant that has previously been found in violation of this chapter pursuant to RSA 485-A:22-a or an application that does not otherwise comply with the department's rules relative to the permit application process.
   II-c. Beginning October 1, 2007 and each fiscal quarter thereafter, the department shall submit a quarterly report to the house and senate finance committees, the house resources, recreation, and economic development committee, and the senate energy, environment, and economic development committee relative to administration of the terrain alteration review program.
   III. Normal agricultural operations shall be exempt from the provisions of this section. The department may exempt other state agencies from the permit and fee provisions of this section provided that each such agency has incorporated appropriate protective practices in its projects which are substantially equivalent to the requirements established by the department under this chapter.
   IV. Timber harvesting operations shall be exempt from the fee provisions of this section. Timber harvesting operations shall be considered in compliance with this section and shall be issued a permit by rule provided such operations are in accordance with procedures prescribed in the Best Management Practices for Erosion Control on Timber Harvesting Operations in New Hampshire, published by the department of resources and economic development, and provided that the department of revenue administration's intent to cut form is signed.
   V. Trail construction operations for the purposes of modifying existing biking and walking trails shall be exempt from the provisions of this section. Such operations shall be considered in compliance with this section and shall be issued a general permit by rule provided such operations are implemented by a non-profit organization, municipality, or government entity, are limited to a disturbed area no more than 12 feet in width, and are in accordance with procedures prescribed in the Best Management Practices For Erosion Control During Trail Maintenance and Construction, published by the department of resources and economic development, bureau of trails in 2004.

Source. 1989, 339:1. 1992, 157:3. 1996, 228:106, 109, eff. July 1, 1996. 2003, 224:5, eff. July 1, 2003. 2005, 32:1, eff. July 9, 2005. 2007, 263:30, eff. Jan. 1, 2008. 2009, 208:3, eff. Sept. 13, 2009.