40.6462 - Access to residence or appurtenance with alleged defect after notice of defect is given; effect on owners who did not provide notice.
40.6462 Access to residence or appurtenance with alleged defect after notice of defect is given; effect on owners who did not provide notice.
1. Except as otherwise provided in subsection 2, after notice of a constructional defect is given to a contractor pursuant to NRS 40.645, the claimant shall, upon reasonable notice, allow the contractor and each subcontractor, supplier or design professional who may be responsible for the alleged defect reasonable access to the residence or appurtenance that is the subject of the notice to determine the nature and extent of a constructional defect and the nature and extent of repairs that may be necessary. To the extent possible, the persons entitled to inspect shall coordinate and conduct the inspections in a manner which minimizes the inconvenience to the claimant.
2. If notice is given to the contractor pursuant to subsection 4 of NRS 40.645, the contractor and each subcontractor, supplier or design professional who may be responsible for the defect do not have the right to inspect the residence or appurtenance of an owner who is not named in the notice unless the owner requests the inspection in the manner set forth in NRS 40.6452. If the owner does not request the inspection, the owner shall be deemed not to have provided notice pursuant to NRS 40.645.
(Added to NRS by 2003, 2036)