40.646 - Notice of defect to be forwarded by contractor to subcontractor, supplier or design professional; effect of failure to forward notice; inspection of alleged defect; election to repair.

40.646  Notice of defect to be forwarded by contractor to subcontractor, supplier or design professional; effect of failure to forward notice; inspection of alleged defect; election to repair.

      1.  Except as otherwise provided in subsection 2, not later than 30 days after the date on which a contractor receives notice of a constructional defect pursuant to NRS 40.645, the contractor shall forward a copy of the notice by certified mail, return receipt requested, to the last known address of each subcontractor, supplier or design professional whom the contractor reasonably believes is responsible for a defect specified in the notice.

      2.  If a contractor does not provide notice as required pursuant to subsection 1, the contractor may not commence an action against the subcontractor, supplier or design professional related to the constructional defect unless the contractor demonstrates that, after making a good faith effort, the contractor was unable to identify the subcontractor, supplier or design professional whom the contractor believes is responsible for the defect within the time provided pursuant to subsection 1.

      3.  Except as otherwise provided in subsection 4, not later than 30 days after receiving notice from the contractor pursuant to this section, the subcontractor, supplier or design professional shall inspect the alleged constructional defect in accordance with subsection 1 of NRS 40.6462 and provide the contractor with a written statement indicating:

      (a) Whether the subcontractor, supplier or design professional has elected to repair the defect for which the contractor believes the subcontractor, supplier or design professional is responsible; and

      (b) If the subcontractor, supplier or design professional elects to repair the defect, an estimate of the length of time required for the repair, and at least two proposed dates on and times at which the subcontractor, supplier or design professional is able to begin making the repair.

      4.  If the notice of a constructional defect forwarded by the contractor was given pursuant to subsection 4 of NRS 40.645 and the contractor provides a disclosure of the notice of the alleged common constructional defects to the unnamed owners to whom the notice may apply pursuant to NRS 40.6452:

      (a) The contractor shall, in addition to the notice provided pursuant to subsection 1, upon receipt of a request for an inspection, forward a copy of the request to or notify each subcontractor, supplier or design professional who may be responsible for the alleged defect of the request not later than 5 working days after receiving such a request; and

      (b) Not later than 20 days after receiving notice from the contractor of such a request, the subcontractor, supplier or design professional shall inspect the alleged constructional defect in accordance with subsection 2 of NRS 40.6462 and provide the contractor with a written statement indicating:

             (1) Whether the subcontractor, supplier or design professional has elected to repair the defect for which the contractor believes the subcontractor, supplier or design professional is responsible; and

             (2) If the subcontractor, supplier or design professional elects to repair the defect, an estimate of the length of time required for the repair, and at least two proposed dates on and times at which the subcontractor, supplier or design professional is able to begin making the repair.

      5.  If a subcontractor, supplier or design professional elects to repair the constructional defect, the contractor or claimant may hold the subcontractor liable for any repair which does not eliminate the defect.

      (Added to NRS by 2003, 2035)