338.535 - Public body to provide notice concerning progress payments and retainage payments to certain subcontractors and suppliers.

338.535  Public body to provide notice concerning progress payments and retainage payments to certain subcontractors and suppliers.  Within 5 working days after a public body receives a written request from a subcontractor or supplier of the contractor with respect to a contract which has not been fully performed, the public body shall notify the subcontractor or supplier in writing of the following:

      1.  The date the public body made a specified progress payment or retainage payment to a contractor;

      2.  Whether the public body has paid the entire amount of a specified progress payment or retainage payment to the contractor; and

      3.  The amount withheld by the public body from a specified progress payment or retainage payment to the contractor, if any.

      (Added to NRS by 1999, 1985)