338.1699 - Subcontractors on public works for which construction manager at risk was awarded contract: Eligibility; submission of list to local government. [Effective through June 30, 2011.]
338.1699 Subcontractors on public works for which contractor at risk was awarded contract: Eligibility; submission of list to public body. [Effective July 1, 2011.]
1. To be eligible to provide materials, equipment, work or other services on a public work for which a construction manager at risk was awarded a contract pursuant to NRS 338.1696, a subcontractor must be:
(a) Licensed pursuant to chapter 624 of NRS; and
(b) Selected by the construction manager at risk based on the process of competitive bidding set forth in the applicable provisions of NRS 338.1373 to 338.148, inclusive.
2. A construction manager at risk to whom a contract for the construction of a public work is awarded pursuant to NRS 338.1696 shall submit to the public body that awarded the contract a list containing the names of each subcontractor with whom the construction manager at risk intends to enter into a contract for the provision of materials, equipment, work or other services on the public work.
(Added to NRS by 2007, 2895; A 2009, 441, effective July 1, 2011)