90-4-1221. Requirements prior to project construction.
90-4-1221. Requirements prior to project construction. Prior to starting construction under this part, the governmental body shall enter into a contract or contracts:
(1) with a transmission services provider to interconnect with the transmission or distribution facilities of a utility or cooperative;
(2) that ensure that all ancillary services as required by the control area operator are available to regulate the generation of electricity from the project;
(3) for the sale of electricity from the project; and
(4) with a tribal government for projects being constructed within the exterior boundaries of that tribal government's Indian reservation.
History: En. Sec. 16, Ch. 378, L. 2007.