82-11-183. Certificate of completion -- department of environmental quality participation -- transfer of liability.
82-11-183. (Effective on occurrence of contingency) Certificate of completion -- department of environmental quality participation -- transfer of liability. (1) Pursuant to subsection (3), after carbon dioxide injections into a reservoir end and upon completion of the certification requirements pursuant to subsections (4) and (5), the board shall issue the geologic storage operator a certificate of project completion.
(2) The board:
(a) shall adopt rules pursuant to 82-11-111 necessary for implementing subsection (4) of this section, including rules for public notice and hearing; and
(b) may, pursuant to 82-11-111, adopt any other rules necessary for administration of this section.
(3) The certificate may not be issued until at least 15 years after carbon dioxide injections end.
(4) Subject to subsection (5), the certificate may be issued only if the geologic storage operator:
(a) is in full compliance with regulations governing the geologic storage reservoir pursuant to this part;
(b) shows that the geologic storage reservoir will retain the carbon dioxide stored in it;
(c) shows that all wells, equipment, and facilities to be used in the postclosure period are in good condition and retain mechanical integrity;
(d) shows that it has plugged wells, removed equipment and facilities, and completed reclamation work as required by the board;
(e) shows that the carbon dioxide in the geologic storage reservoir has become stable, which means that it is essentially stationary or chemically combined or, if it is migrating or may migrate, that any migration will not cross the geologic storage reservoir boundary; and
(f) shows that the geologic storage operator will continue to provide adequate bond or other surety after receiving the certificate of completion for at least 15 years following issuance of the certificate of completion and that the operator continues to accept liability for the geologic storage reservoir and the stored carbon dioxide.
(5) (a) Prior to issuing a certificate of completion, the board shall solicit, document, consider, and address comments from the department of environmental quality.
(b) Notwithstanding subsection (5)(a), the board makes the final decision on issuance of the certificate.
(6) After issuing a certificate of completion, the board shall ensure adequate monitoring by the operator of the wells and reservoir, verifying compliance with subsection (4), for a period of 15 years.
(7) (a) Following the monitoring and verification required in subsection (6) and subject to subsections (7)(b) and (7)(c), if the geologic storage operator has title to the geologic storage reservoir and the stored carbon dioxide, the geologic storage operator may transfer title to the geologic storage reservoir and to the stored carbon dioxide to the state.
(b) Prior to a transfer of title, the monitoring pursuant to subsection (6) must show that:
(i) the reservoir and wells are in full compliance with regulations pursuant to this part; and
(ii) the reservoir will maintain its structural integrity and will not allow carbon dioxide to move out of one stratum into another or pollute drinking water supplies.
(c) (i) Prior to a transfer of title, the board shall solicit, document, consider, and address comments from the department of environmental quality.
(ii) The board shall make a recommendation to the board of land commissioners as to whether title should transfer to the state.
(iii) Notwithstanding subsections (7)(c)(i) and (7)(c)(ii), the board of land commissioners shall make the final decision on the transfer of title.
(8) If liability is transferred pursuant to subsection (7):
(a) title is transferred, without payment or any compensation, to the state;
(b) title acquired by the state includes all rights and interests in and all responsibilities associated with the geologic storage reservoir and the stored carbon dioxide;
(c) the geologic storage operator and all persons who generated any injected carbon dioxide are released from all regulatory requirements and liability associated with the geologic storage reservoir and the stored carbon dioxide;
(d) any bonds or other surety posted by the geologic storage operator must be released; and
(e) monitoring and managing the geologic storage reservoir and the stored carbon dioxide is the state's responsibility to be overseen by the board until the federal government assumes responsibility for the long-term monitoring and management of geologic storage reservoirs and stored carbon dioxide.
(9) (a) If the operator does not transfer title to the state pursuant to subsection (7), the operator indefinitely accepts liability, except as provided in subsection (10), for the stored carbon dioxide and the geologic storage reservoir.
(b) If the operator is found not to be in compliance with subsection (7)(b), the operator retains liability until the operator is able to meet the requirements.
(10) After receiving a certificate of completion, every 15 years after completing the monitoring and verification required by subsection (6), an operator may petition the board and request to transfer liability to the state and be released from liability pursuant to subsection (8). An operator who petitions the board pursuant to this subsection (10) may not request that the fee required by 82-11-181(1) or 82-11-184(2)(b) be remitted.
History: En. Sec. 4, Ch. 474, L. 2009.