18-2-312. Excusable delays.
18-2-312. Excusable delays. A public contractor shall not be considered to be working beyond contract time if the delay is caused by an accident or casualty produced by physical cause which is not preventable by human foresight, i.e., any of the misadventures termed an "act of God".
History: En. Sec. 2, Ch. 141, L. 1967; R.C.M. 1947, 82-1928.