383B.1584 DESIGN-BUILD AWARD.

The county board, after considering the recommendations of the design-build selection panel, shall award the design-build contract to the proposer with the highest scored proposal based on the evaluation criteria in the RFP. The rationale for the selection of the proposal must be stated at the time of the contract award. The county board may reject any or all proposals, but must not do so to evade the other provisions and policies of this section. If the county board rejects all proposals, it may then solicit new proposals after making appropriate modifications to performance criteria, budget constraints, or qualifications.