Section 460.1031 - Extensions of 2015 renewable energy standard deadline; establishment of revised renewable energy standard; compliance; "good cause" defined.

CLEAN, RENEWABLE, AND EFFICIENT ENERGY ACT (EXCERPT)
Act 295 of 2008

460.1031 Extensions of 2015 renewable energy standard deadline; establishment of revised renewable energy standard; compliance; "good cause" defined.

Sec. 31.

(1) Upon petition by an electric provider, the commission may for good cause grant 2 extensions of the 2015 renewable energy standard deadline under section 27. Each extension shall be for up to 1 year.

(2) If 2 extensions of the 2015 renewable energy standard deadline have been granted to an electric provider under subsection (1), upon subsequent petition by the electric provider at least 3 months before the expiration of the second extended deadline, the commission shall, after consideration of prior extension requests under this section and for good cause, establish a revised renewable energy standard attainable by the electric provider. If the electric provider achieves the revised renewable energy standard, the provider is considered to be in compliance with this subpart.

(3) An electric provider that makes a good faith effort to spend the full amount of incremental costs of compliance as outlined in its approved renewable energy plan and that complies with its approved plan, subject to any approved extensions or revisions, shall be considered to be in compliance with this subpart.

(4) As used in this section, "good cause" includes, but is not limited to, the electric provider's inability, as determined by the commission, to meet a renewable energy standard because of a renewable energy system feasibility limitation including, but not limited to, any of the following:

(a) Renewable energy system site requirements, zoning, siting, land use issues, permits, including environmental permits, any certificate of need process under section 6s of 1939 PA 3, MCL 460.6s, or any other necessary governmental approvals that effectively limit availability of renewable energy systems, if the electric provider exercised reasonable diligence in attempting to secure the necessary governmental approvals. For purposes of this subdivision, "reasonable diligence" includes, but is not limited to, submitting timely applications for the necessary governmental approvals and making good faith efforts to ensure that the applications are administratively complete and technically sufficient.

(b) Equipment cost or availability issues including electrical equipment or renewable energy system component shortages or high costs that effectively limit availability of renewable energy systems.

(c) Cost, availability, or time requirements for electric transmission and interconnection.

(d) Projected or actual unfavorable electric system reliability or operational impacts.

(e) Labor shortages that effectively limit availability of renewable energy systems.

(f) An order of a court of competent jurisdiction that effectively limits the availability of renewable energy systems.


History: 2008, Act 295, Imd. Eff. Oct. 6, 2008
Compiler's Notes: Enacting section 1 of Act 295 of 2008 provides:"Enacting section 1. As provided in section 5 of 1846 RS 1, MCL 8.5, this act is severable."