460.1025 Municipally-owned electric utilities; applicability of section; filing of renewable energy plan; requirements; public comment; initial approval; review; amendment; determination of noncompliance.

Sec. 25.

(1) This section applies only to municipally-owned electric utilities.

(2) Each electric provider shall file a proposed renewable energy plan with the commission within 120 days after the commission issues a temporary order under section 171. Two or more electric providers that each serve fewer than 15,000 customers may file jointly. The proposed plan shall meet all of the following requirements:

(a) Describe how the provider will meet the renewable energy standards.

(b) Specify whether the number of megawatt hours of electricity used in the calculation of the renewable energy credit portfolio will be weather-normalized or based on the average number of megawatt hours of electricity sold by the electric provider annually during the previous 3 years to retail customers in this state. Once the commission determines that the proposed plan complies with this act, this option shall not be changed.

(c) Include the expected incremental cost of compliance with the renewable energy standards.

(d) Describe the manner in which the provider will allocate costs.

(3) Subject to subsection (6), the commission shall provide an opportunity for public comment on the proposed plan filed under subsection (2). After the applicable opportunity for public comment and within 90 days after the proposed plan is filed with the commission, the commission shall determine whether the proposed plan complies with this act.

(4) Every 2 years after the commission initially determines under subsection (3) that a renewable energy plan complies with this act, the commission shall review the plan. Subject to subsection (6), the commission shall provide an opportunity for public comment on the plan. After the applicable opportunity for public comment, the commission shall determine whether any amendment to the plan proposed by the provider complies with this act. The proposed amendment is adopted if the commission determines that it complies with this act.

(5) If a provider proposes to amend its renewable energy plan at a time other than during the biennial review process under subsection (4), the provider shall file the proposed amendment with the commission. Subject to subsection (6), the commission shall provide an opportunity for public comment on the amendment. After the applicable opportunity for public comment and within 90 days after the amendment is filed, the commission shall determine whether the proposed amendment to the plan complies with this act. The proposed amendment is adopted if the commission determines that it complies with this act.

(6) The commission need not provide an opportunity for public comment under subsection (3), (4), or (5) if the governing body of the provider has already provided an opportunity for public comment and filed the comments with the commission.

(7) If the commission determines that a proposed plan or amendment under this section does not comply with this act, the commission shall explain in writing the reasons for its determination.


History: 2008, Act 295, Imd. Eff. Oct. 6, 2008