Section 12-605 - Electrical inspection certificates.
§ 12-605. Electrical inspection certificates.
(a) Before authorizing electrical current to be turned on.- Before a utility authorizes electrical current to be turned on for a premise or structure, the utility must receive a cut-in certificate from a certified nongovernmental electrical inspector or governmental unit that is qualified to issue electrical inspection certificates.
(b) After completion of electrical installation.- Within 15 days after completion, each electrical installation shall be certified by a certified nongovernmental electrical inspector or a governmental unit that is qualified to issue electrical inspection certificates.
[2010, ch. 127.]