45A.180 Selection of method of construction contracting management.
Loading PDF...
methods of management of construction contracting as he or she may determine to
be feasible; setting forth criteria to be used in determining which method of
management of construction is to be used for a particular project; establishing a
model process parallel to the selection committee procedures established in
45A.810 for the procurement of alternative project services of "construction
management-at-risk" and "design-build," and for a "construction manager-agency;"
and providing that the chief purchasing officer shall execute and include in the
contract file a written statement setting forth the facts recommending that a
particular method of management of construction contracting be used. The
administrative regulations shall include the establishment of:
(a) The relative weighing between qualifications and price, including the reciprocal preference for resident bidders required under KRS 45A.494; and (b) The level of stipend, if any, available for the various types of projects. (2) When a request for proposal for a project utilizing an alternative project delivery method is issued, the contracting body shall transmit a copy of the request for
proposal to the Capital Projects and Bond Oversight Committee staff. (3) Upon issuance of the contract for a project utilizing an alternative project delivery method, the contracting body shall submit the contract to the Government Contract
Review Committee for review in accordance with KRS 45A.690 to 45A.725. The
contracting body shall insure the contract clearly identifies to the committee that an
alternative project delivery method is being utilized. Upon disapproval of or
objection to the contract by the committee, the contracting body shall determine
whether the contract shall be revised to comply with the objections of the
committee, be canceled, or remain in effect. Subsequent contract amendments
relating to change orders shall not be required to be submitted to the Government
Contract Review Committee. (4) A request for proposal for a project utilizing an alternative project delivery method under this section shall specifically state the evaluation factors and the relative
weight of each to be used in the scoring of awards. (5) Any governing body of a postsecondary institution that manages its capital construction program under KRS 164A.580 shall adhere to the regulations
promulgated under this section when utilizing an alternative project delivery
method for capital projects, and shall report to legislative committees as specified in
this section. (6) Any corporation as described by KRS 45.750(2)(c) or as created under the Kentucky Revised Statutes as a governmental agency and instrumentality of the
Commonwealth that manages its capital construction program shall adhere to the
regulations promulgated under this section when utilizing an alternative project
delivery method for capital projects, and shall report to legislative committees as
specified in this section. Effective: July 15, 2010
History: Amended 2010 Ky. Acts ch. 162, sec. 10, effective July 15, 2010. -- Amended 2003 Ky. Acts ch. 98, sec. 7, effective June 24, 2003. -- Created 1978 Ky. Acts
ch. 110, sec. 36, effective January 1, 1979.