310.18 - PARTIAL PAYMENTS DURING CONSTRUCTION.

        310.18  PARTIAL PAYMENTS DURING CONSTRUCTION.         Partial payments may be made on work in progress, but no such      partial payment shall be deemed final acceptance of the work nor a      waiver of any defect in the work.  The board of supervisors, the      county engineer, or the department may approve claims.  Approval may      be evidenced by the signature of the county engineer or chairperson      of the board or department, or a majority of the members of the board      or department, on the individual claims or on the abstract of a      number of claims with the individual claims attached to the abstract.      
         Section History: Early Form
         [C39, § 4686.18; C46, 50, 54, 58, 62, 66, 71, 73, 75, 77, 79,      81, § 310.18] 
         Section History: Recent Form
         97 Acts, ch 104, §4