468.104 - ABANDONMENT OF WORK.

        468.104  ABANDONMENT OF WORK.         In case any contractor abandons or fails to proceed diligently and      properly with the work before completion, or in case the contractor      fails to complete the same in the time and according to the terms of      the contract, the board shall make written demand on the contractor      and the contractor's surety to proceed with the work within ten days.      Service of said demand may be personal, or by certified mail      addressed to the contractor and the surety, respectively, at their      places of residence or business, as shown by the records in the      auditor's office.  
         Section History: Early Form
         [S13, § 1944, 1989-a10; C24, 27, 31, 35, 39, § 7535; C46, 50,      54, 58, 62, 66, 71, 73, 75, 77, 79, 81, § 455.114] 
         Section History: Recent Form
         89 Acts, ch 126, § 2         CS89, § 468.104         Referred to in § 357.17