CHAPTER 23. DEPARTMENT ACTION ON CERTIFICATION APPLICATIONS

IC 13-18-23
     Chapter 23. Department Action on Certification Applications

IC 13-18-23-1
Deadline for department action; statement of reasons; waiver
    
Sec. 1. (a) The department shall:
        (1) make a final determination on an application for a certification under Section 401 of the Clean Water Act not later than one hundred twenty (120) days after its receipt of a complete application; and
        (2) include in its notice of the final determination to the applicant a statement of reasons for the final determination.
    (b) A failure by the department to act within the period specified in subsection (a)(1) constitutes a waiver of the certification.
As added by P.L.282-2003, SEC.39.