(415 ILCS 10/2) (from Ch. 85, par. 5902)
Sec. 2. As used in this Act, unless the context clearly indicates otherwise:
(1) "Solid waste" means "waste", as defined in the Illinois Environmental Protection Act, but for the purposes of this Act does not include "hazardous waste" as defined in that Act.
(2) "Unit of local government" means a municipality, county, or a Municipal Joint Action Agency created under Section 3.2 of the Intergovernmental Cooperation Act or, if the context requires, the member municipalities of such an agency or their territory.
(3) "Pollution control facility" has the meaning ascribed to the term in the Illinois Environmental Protection Act, except that the term shall not include sewers and sewage treatment facilities owned or operated by sanitary districts.
(4) "Jurisdiction" means: (1) in the case of a municipality, the territory within the corporate limits of the municipality; (2) in the case of a county, the territory within the corporate limits of the county which does not lie within the corporate limits of any municipality which has adopted and is implementing a plan under this Act either independently or through a Municipal Joint Action Agency; and (3) in the case of a Municipal Joint Action Agency, the territory within the corporate limits of each member municipality.
(5) "Qualified solid waste energy facility" means either (i) a solid waste pollution control facility or a portion thereof owned or operated by or for the benefit of a unit of local government and developed under this Act, which meets the requirements set forth in Section 3.1 of this Act, or (ii) a facility which uses methane gas generated from landfills.
(6) "Municipal waste" means garbage, general household, institutional and commercial waste, industrial lunchroom or office waste, landscape waste, and construction and demolition debris.
(Source: P.A. 87‑650; 88‑681, eff. 12‑22‑94.) |
(415 ILCS 10/3) (from Ch. 85, par. 5903)
Sec. 3. Units of local government may, on their own behalf or pursuant to an intergovernmental agreement under Section 4, prepare solid waste management plans for disposal of solid waste generated within their jurisdictions. No such plans, however, shall be implemented prior to July 1, 1986. Such plans, if prepared, shall include provisions for, but need not be limited to, the following:
(1) a description of the origin, content and weight |
| or volume of municipal waste currently generated within the unit of local government's boundaries, and an estimate of the origin, content, and weight or volume of municipal waste that will be generated within the unit of local government's boundaries during the next 20 years, including an assessment of the primary variables affecting this estimate and the extent to which they can reasonably be expected to occur; | |
(2) a description of the facilities where municipal |
| waste is currently being processed or disposed of and the remaining capacity of such facilities; | |
(3) a description of the facilities and programs |
| that are proposed for the management of municipal waste generated within the unit of local government's boundaries during the next 20 years including, but not limited to, their size, expected cost and financing method; | |
(4) an evaluation of the environmental, energy, life |
| cycle cost and economic advantages and disadvantages of the proposed waste management facilities and financing method; | |
(5) a description of the time schedule for the |
| development and operation of each proposed facility or program; | |
(6) the identity of potential sites within the unit |
| of local government where each proposed waste processing, disposal and recycling program will be located, or an explanation of how the sites will be chosen. For any facility outside the unit of local government that the unit of local government proposes to utilize, the plan shall explain the reasons for selecting that facility; | |
(7) if the plan concludes that waste stream control |
| measures are necessary to implement the plan, the identification of those measures; | |
(8) identification of any governmental entity that |
| will be responsible for implementing the plan on behalf of the unit of local government, and an explanation of the legal basis for the entity's authority to do so; and | |
(9) adequate provision for the present and |
| reasonably anticipated future needs of the recycling and resource recovery interests within the area. | |
(Source: P.A. 87‑650.) |
(415 ILCS 10/3.1) (from Ch. 85, par. 5903.1)
Sec. 3.1. If a solid waste management plan prepared and implemented under Section 3 of this Act, Section 2 of the Illinois Solid Waste Management Act, Section 22.15 of the Environmental Protection Act, or Section 4 of the Solid Waste Planning and Recycling Act, or the Energy Facility Plan, specifies that incineration shall be a means used by a facility to meet waste disposal needs within a jurisdiction, that facility shall be deemed a qualified solid waste energy facility if it meets the following requirements:
(1) The operator annually certifies to the Illinois Commerce Commission that solid waste is the primary fuel and comprises no less than 95% of the annual fuel loading.
(2) The operator guarantees that the solid waste throughput volume shall be equal to at least 66% of the design capacity of the facility.
(3) (A) A solid waste management plan has been developed |
| by the unit or units of local government included in the area that is intended to be served by the facility and has been filed with and approved by the Illinois Environmental Protection Agency pursuant to subsection (g) of Section 22.15 of the Illinois Environmental Protection Act or pursuant to Section 5 of the Solid Waste Planning and Recycling Act. Any such plan shall establish a recycling goal of a minimum of 25% by weight of the solid waste stream generated within the planning area; or | |
(B) For any facility that receives local site |
| approval before May 1, 1989, a Solid Waste Energy Facility Plan has been developed with respect to the facility by the owner or operator of the facility and has been filed with and approved by the Illinois Environmental Protection Agency. Any such Solid Waste Energy Facility Plan shall establish a recycling goal of at least 25% of the solid waste stream received by the Solid Waste Energy Facility, and shall include a description of the processes and systems to be utilized by the facility for materials and energy recovery. | |
(4) A good faith effort has been made by the unit or units of local government served by the facility or the owner or operator of the facility to achieve the 25% recycling goal at the time the facility commences commercial operation and thereafter.
(Source: P.A. 91‑357, eff. 7‑29‑99.) |