(a) Nothing in this part shall create any cause of action on behalf of any claimant or contractor.
(b) This part does not apply to a contractor's right to seek contribution, indemnity, or recovery against a subcontractor, supplier, or design professional for any claim made against a contractor by a claimant.
(c) In the event of any conflict or inconsistency between the provisions of this part and the provisions of any contract between a claimant and a contractor, the provisions of the contract shall govern and control.
(d) This part shall not apply to a contractor who is not required to be licensed under Chapter 41 of Title 43.