Sec. 49-41c. State contractor to make payment to subcontractor within thirty days.
Sec. 49-41c. State contractor to make payment to subcontractor within thirty
days. Any person contracting with the state shall make payment to any subcontractor
employed by such contractor within thirty days of payment by the state to the contractor
for any work performed or, in the case of any contract entered into on or after October
1, 1986, for materials furnished by such subcontractor, provided such contractor may
withhold such payment if such contractor has a bona fide reason for such withholding
and if such contractor notifies the affected subcontractor, in writing, of his reasons for
withholding such payment and provides the state board, commission, department, office,
institution, council or other agency through which such contractor had made the contract,
with a copy of the notice, within such thirty-day period.
(P.A. 83-552, S. 1; P.A. 86-12, S. 2.)
History: P.A. 86-12 made section applicable to payment for materials as well as labor.
See chapter 60, part II (Sec. 4b-91 et seq.) re public building contracts.
Sec. 49-41a et seq., "prompt payment act" cited. 238 C. 293. Sec. 49-41 et seq. cited. 239 C. 708.