Sec. 22a-6f. Fees. Due dates. Late payments. Application. Waiver. (a) Each
annual fee charged by the Commissioner of Environmental Protection pursuant to the
general statutes shall be due on or before July first of each year, unless otherwise specified in the general statutes or in regulations adopted pursuant thereto. The fee for late
payment of an annual fee charged by said commissioner pursuant to the general statutes
shall be ten per cent of the annual fee due, plus one and one-quarter per cent per month
or part thereof that the annual fee remains unpaid. Each permit fee and permit application
fee charged by the commissioner pursuant to the general statutes is due upon the submission of the permit application, unless otherwise specified in the general statutes or in
regulations adopted pursuant thereto. Each permit fee and permit application fee payable
to the commissioner shall apply equally to the issuance, renewal, modification and transfer of a permit unless otherwise specified in the general statutes or in regulations adopted
pursuant thereto. The commissioner may waive any fee payable to him as it applies to
the activities of an agency, board, commission, council or department of the state, provided such agency, board, commission, council or department compensates the Department of Environmental Protection in an amount equal to such fee pursuant to a written
agreement.
(b) Notwithstanding any provision of the general statutes or any regulation adopted
under this title, on and after August 20, 2003, each fee in effect pursuant to regulations
adopted pursuant to any section of this title that is greater than one hundred dollars shall
be increased by fifty per cent and all such fees of one hundred dollars or less shall be
doubled, provided no such fee shall be less than one hundred dollars.
(c) Notwithstanding the provisions of subsection (b) of this section: (1) The fees
and annual adjustment for Title V emissions shall be assessed pursuant to the regulations
adopted under section 22a-174; (2) each fee imposed pursuant to a general permit, in
effect on or before August 20, 2003, shall be double the amount specified in such permit;
and (3) each fee imposed pursuant to a certificate of permission, issued in accordance
with section 22a-363b, shall be double the amount in effect on or before August 20, 2003.
(d) Unless otherwise specified in a general permit, the registration fee for a general
permit shall be as follows: (1) If the person intending to engage in the regulated activity
is required to register with the Department of Environmental Protection and obtain
approval of the registration before the activity is authorized, one thousand dollars; or
(2) if the person intending to engage in the regulated activity is only required to register
with the Department of Environmental Protection before the activity is authorized, five
hundred dollars. No fee for a general permit shall exceed five thousand dollars.
(e) Unless otherwise established by regulations adopted pursuant to section 22a-354i, the fee for a permit of a regulated activity, as described in section 22a-354i, shall be
one thousand dollars and the fee to register such regulated activity with the Department of
Environmental Protection, pursuant to section 22a-354i, shall be five hundred dollars.
(f) The fee for a consolidated general permit issued in accordance with more than
one section of this title shall be specified in such general permit and shall not exceed
the total sum for individual general permits, as authorized pursuant to subdivision (2)
of subsection (c) of this section.
(P.A. 91-369, S. 33, 36; P.A. 96-145, S. 3; June 30 Sp. Sess. P.A. 03-6, S. 152.)
History: P.A. 96-145 amended Subsec. (a) to provide for late payments of fees and added Subsec. (b) re fees for general
permits; June 30 Sp. Sess. P.A. 03-6 replaced former Subsec. (b) re fee for registration pursuant to a general permit with
new Subsec. (b) re increase in fees in effect pursuant to regulations, added new Subsec. (c) re fees for Title V emissions,
the doubling of existing fees for general permits, and fees for a certificate of permission, added new Subsec. (d) re registration
fees for a general permit, added new Subsec. (e) re fees for a permit of a regulated activity in an aquifer protection area,
and added new Subsec. (f) re fees for a consolidated general permit, effective August 20, 2003.