Sec. 16-243w. Advanced metering system plan and deployment.
Sec. 16-243w. Advanced metering system plan and deployment. (a) On or before July 1, 2007, each electric distribution company shall submit a plan to the Department of Public Utility Control to deploy an advanced metering system. In lieu of submitting a plan pursuant to this section, an electric distribution company may seek a
determination by the department that such company's existing metering system meets
the requirements of this section. Such metering systems shall support net metering and
be capable of tracking hourly consumption to support proactive customer pricing signals
through innovative rate design, such as time-of-day or real-time pricing of electric service for all customer classes.
(b) Each plan to implement an advanced metering system developed pursuant to
subsection (a) of this section shall outline an implementation schedule whereby meters
and any network necessary to support such meters are fully deployed on or before January 1, 2009. On or after January 1, 2009, any customer may obtain a meter on demand.
(c) The cost of the advanced metering system, including, but not limited to, the
meters, the network to support the meters, software and vendor costs to obtain the required information from the metering system and administrative, installation, operation
maintenance costs, shall be borne by the electric distribution company and shall be
recoverable in rates. Any unrecovered cost of the current metering system shall continue
to be reflected in rates.
(d) Not later than six months after June 4, 2007, electric distribution companies,
competitive electric suppliers and aggregators shall offer time-of-use pricing options
to all customer classes. These pricing options shall include, but not be limited to, hourly
and real-time pricing options.
(P.A. 07-242, S. 98.)
History: P.A. 07-242 effective June 4, 2007.