2821-2829
PUBLIC UTILITIES CODE
SECTION 2821-2829
2821. (a) The commission shall approve and establish equitable charges to be paid by an electrical corporation which purchases electricity or electrical generating capacity, or both, from any private energy producer employing other than a conventional power source for the generation of electricity. (b) The commission, on its own motion or on application of an electrical corporation or a private energy producer, may also specify the prices, terms, and conditions for the purchase or sale of electricity or electrical generating capacity, or both, between an electrical corporation and a private energy producer, and these prices, terms, and conditions, so specified, shall be considered reasonable and prudent for all purposes. The commission may act to specify these prices, terms, and conditions on its own motion or on application of an electrical corporation or a private energy producer. (c) Every private energy producer employing hydroelectric facilities, who executes a contract with an electrical corporation on or after January 1, 1988, or prior to that date, for the purchase of electricity or electrical generating capacity, or both, shall obtain and provide proof of compliance by the private energy producer with all state laws relating to the control, appropriation, use, and distribution of water, including, but not limited to, the obtaining of applicable licenses and permits. The private energy producer shall also provide proof of compliance with the federal Clean Water Act. (d) (1) For the purpose of providing proof of compliance with all state laws relating to the control, appropriation, use, and distribution of water, the electrical corporation shall require the private energy producer to provide either of the following: (A) Certification from the State Water Resources Control Board that a water right permit has been issued for the operation of the hydroelectric facility. (B) Certification from the State Water Resources Control Board that, in the opinion of the board, the private energy producer possesses riparian rights or other water rights which authorize the operation of the hydroelectric facility. (2) The requirements of paragraph (1) shall apply only to contracts involving hydroelectric projects which have not been accepted by the electrical corporation for commercial operation prior to May 18, 1987. (3) Every contract executed by a private energy producer who is in violation of paragraph (1) is void and unenforceable on and after whichever of the following dates applies: (A) February 29, 1988, for contracts involving hydroelectric projects which have been accepted by the electrical corporation for commercial operation on or after May 18, 1987, and prior to January 1, 1988. (B) The 60th day after a project has been accepted by the electrical corporation for commercial operation, for contracts involving hydroelectric projects which are accepted by the electrical corporation for commercial operation on or after January 1, 1988. (4) The commission shall disallow, for purposes of establishing rates for an electrical corporation, all amounts expended for the purchase of electricity pursuant to a contract that is void and unenforceable under this subdivision. (e) (1) For the purposes of providing proof of compliance with the federal Clean Water Act, the electrical corporation shall require the private energy producer to provide a statement from the State Water Resources Control Board that certification pursuant to Section 401 of the federal Clean Water Act has either been granted or waived by the board for operation of the hydroelectric facility. The board shall not waive certification unless the board finds that there is reasonable assurance that the project shall comply with all applicable requirements of the federal Clean Water Act and state water quality laws. If the board cannot make this finding within the period provided for certification, the board shall either certify upon conditions that provide reasonable assurance of compliance or deny certification. (2) The requirements of paragraph (1) shall apply only to contracts involving hydroelectric projects which have not been accepted by the electrical corporation for commercial operation prior to January 1, 1992. (3) Every contract executed by a private energy producer who is in violation of paragraph (1) is void and unenforceable on and after whichever of the following dates applies: (A) March 1, 1993, for contracts involving hydroelectric projects which are accepted by the electrical corporation for commercial operation between January 1, 1992, and December 31, 1992. (B) The 60th day after having been accepted by the electrical corporation for commercial operation, for contracts involving hydroelectric projects which are accepted by the electrical corporation for commercial operation on or after January 1, 1993. (4) The commission shall disallow, for purposes of establishing rates for an electrical corporation, all amounts expended for the purchase of electricity pursuant to a contract that is void and unenforceable under this subdivision. (f) Subdivision (d) does not apply to any private energy producer if all of the following conditions are met: (1) The electrical corporation did not make timely written demand for the proof of compliance required by paragraph (1) of subdivision (d). (2) On or before the date the project was accepted by the electrical corporation for commercial operation, the private energy producer was in fact in compliance with all applicable state laws relating to the control, appropriation, use, and distribution of water, including, but not limited to, those laws that require the obtaining of all applicable entitlements. (3) Prior to October 14, 1991, the private energy producer has provided proof of the applicable certification from the State Water Resources Control Board pursuant to subparagraph (A) of paragraph (1) of subdivision (d), which proof contains further certification from the State Water Resources Control Board of the existence of the condition identified in paragraph (2) of subdivision (f). (g) For purposes of meeting the requirements of subdivision (d) or (e), or of providing certification required under Section 26013 of the Public Resources Code, the private energy producer shall furnish information as is reasonably required by the State Water Resources Control Board to document a claim of right, a certification, or a waiver. Every private energy producer requesting certification and a statement from the board pursuant to subdivisions (d) and (e), or to Section 26013 of the Public Resources Code, shall pay to the board at the time of filing the request, a fee of two hundred fifty dollars ($250) to cover the reasonable cost of the board in evaluating and processing the certification request. (h) As used in this section, "Federal Clean Water Act" means the federal Water Pollution Control Act (Sections 1251 et seq. of Volume 33 of the United States Code) and acts amendatory thereof or supplementary thereto. 2821.5. The Legislature finds and declares all of the following: (a) Small power producers provide important alternative sources of electrical energy. (b) The commission is required to approve and establish equitable charges to be paid by electrical corporations which purchase electricity or electrical generating capacity, or both, from qualifying small power producers. (c) The commission recognized the importance of developing standard offer contracts based on long-run avoided costs in order to encourage the development of qualifying small power producers. On September 7, 1983, in Decision 83-09-054, the commission approved interim standard offer No. 4, which established a long-term power purchase contract. (d) Many pioneer small power producers operating prior to September 7, 1983, did so under power purchase contracts based on short-term energy prices and long-term capacity prices. When interim standard offer No. 4 was approved, the commission allowed its provisions to be offered to qualified facility projects which had not yet obtained construction financing or otherwise entered a contract and started construction. Pioneer small power producers with existing contracts were not allowed to switch to the new interim standard offer No. 4 until their existing contracts were no longer in effect. (e) On April 17, 1985, pursuant to Decision 85-04-075, the commission suspended all payment options offered under interim standard offer No. 4 due to the contrasting of excessive energy capacity, and the conclusion that prices were too high. (f) Many qualifying small power producers who were operating under contracts made prior to September 7, 1983, were thus precluded by the commission from adopting interim standard offer No. 4, and may be required to accept new prices and terms which provide less compensation than the suspended interim standard offer No. 4. (g) These financially stressed qualifying small power producers assert they were unfairly denied the opportunity to adopt interim standard offer No. 4 by the commission. They also assert that much of the capacity contracted for under the suspended interim standard offer No. 4 will never be constructed. They further allege that they are being forced to close small powerplants which are currently in operation while producers with interim standard offer No. 4 contracts are constructing new plants. 2822. The commission shall approve and establish standby charges for electrical corporations. The commission may act in this regard on its own motion or on application of an electrical corporation or a private energy producer. 2823. The commission shall approve and establish charges for transmission service. The commission may act in this regard on its own motion or on application of an electrical corporation or a private energy producer. 2824. (a) The commission shall conduct a review of the charges paid by electrical corporations for electricity generated from other than conventional power sources and furnished to such corporations. Following such review, the commission shall consider adjustments in such charges to encourage the generation of electricity from other than conventional power sources. (b) The commission shall conduct a review of standby charges charged by electrical corporations. Following such review, the commission shall consider adjustments in such charges to encourage the utilization of electricity generated from other than conventional power sources and to enable electrical corporations to review the costs of providing standby service. (c) The commission shall conduct a review of charges for transmission service made by electrical corporations for the transmission of electricity generated from other than conventional power sources. Following such review, the commission shall consider adjustments in such charges to encourage the generation of electricity from other than conventional power sources. 2826. (a) The commission shall establish requirements for the administration of power purchase contracts between electrical corporations and private energy producers. For any project which has not received all regulatory permits at the time of the commission's review of a proposed project deferral agreement, the commission shall, at a minimum, apply both of the following requirements: (1) Prohibit payments by an electrical corporation to a private energy producer to defer the construction of a private energy project unless the private energy producer agrees to repay all deferral payments charged to ratepayers in the event the project is not constructed and operating by the time the deferral period expires. (2) Require the private energy producer to provide adequate security to ensure repayment of those ratepayer charges. (b) Subdivision (a) does not apply to a power purchase contract between an electrical corporation and a private energy producer which is a major customer of the electrical corporation, if the contract is negotiated pursuant to procedures prescribed by the commission and for the purpose of retaining that customer. 2826.5. (a) As used in this section, the following terms have the following meanings: (1) "Benefiting account" means an electricity account, or more than one account, mutually agreed upon by Pacific Gas and Electric Company and the City of Davis. (2) "Bill credit" means credits calculated based upon the electricity generation component of the rate schedule applicable to a benefiting account, as applied to the net metered quantities of electricity. (3) "PVUSA" means the photovoltaic electricity generation facility selected by the City of Davis, located at 24662 County Road, Davis, California, with a rated peak electricity generation capacity of 600 kilowatts, and as it may be expanded, not to exceed one megawatt of peak generation capacity. (4) "Net metered" means the electricity output from the PVUSA. (5) "Environmental attributes" associated with the PVUSA include, but are not limited to, the credits, benefits, emissions reductions, environmental air quality credits, and emissions reduction credits, offsets, and allowances, however entitled resulting from the avoidance of the emission of any gas, chemical, or other substance attributable to the PVUSA. (b) The City of Davis may elect to designate a benefiting account, or more than one account, to receive bill credit for the electricity generated by the PVUSA, if all of the following conditions are met: (1) A benefiting account receives service under a time-of-use rate schedule. (2) The electricity output of the PVUSA is metered for time of use to allow allocation of each bill credit to correspond to the time-of-use period of a benefiting account. (3) All costs associated with the metering requirements of paragraphs (1) and (2) are the responsibility of the City of Davis. (4) All electricity delivered to the electrical grid by the PVUSA is the property of Pacific Gas and Electric Company. (5) PVUSA does not sell electricity delivered to the electrical grid to a third party. (6) The right, title, and interest in the environmental attributes associated with the electricity delivered to the electrical grid by the PVUSA are the property of Nuon Renewable Ventures USA, LLC. (c) A benefiting account shall be billed on a monthly basis, as follows: (1) For all electricity usage, the rate schedule applicable to the benefiting account, including any surcharge, exit fee, or other cost recovery mechanism, as determined by the commission, to reimburse the Department of Water Resources for purchases of electricity, pursuant to Division 27 (commencing with Section 80000) of the Water Code. (2) The rate schedule for the benefiting account shall also provide credit for the generation component of the time-of-use rates for the electricity generated by the PVUSA that is delivered to the electrical grid. The generation component credited to the benefiting account may not include the surcharge, exit fee, or other cost recovery mechanism, as determined by the commission, to reimburse the Department of Water Resources for purchases of electricity, pursuant to Division 27 (commencing with Section 80000) of the Water Code. (3) If in any billing cycle, the charge pursuant to paragraph (1) for electricity usage exceeds the billing credit pursuant to paragraph (2), the City of Davis shall be charged for the difference. (4) If in any billing cycle, the billing credit pursuant to paragraph (2), exceeds the charge for electricity usage pursuant to paragraph (1), the difference shall be carried forward as a credit to the next billing cycle. (5) After the electricity usage charge pursuant to paragraph (1) and the credit pursuant to paragraph (2) are determined for the last billing cycle of a calendar year, any remaining credit resulting from the application of this section shall be reset to zero. (d) Not more frequently that once per year, and upon providing Pacific Gas and Electric Company with a minimum of 60 days notice, the City of Davis may elect to change a benefiting account. Any credit resulting from the application of this section earned prior to the change in a benefiting account that has not been used as of the date of the change in the benefit account, shall be applied, and may only be applied, to a benefiting account as changed. (e) Pacific Gas and Electric Company shall file an advice letter with the Public Utilities Commission, that complies with this section, not later than 10 days after the effective date of this section, proposing a rate tariff for a benefiting account. The commission, within 30 days of the date of filing, shall approve the proposed tariff, or specify conforming changes to be made by Pacific Gas and Electric Company to be filed in a new advice letter. (f) The City of Davis may terminate its election pursuant to subdivision (b), upon providing Pacific Gas and Electric Company with a minimum of 60 days notice. Should the City of Davis sell its interest in the PVUSA, or sell the electricity generated by the PVUSA, in a manner other than required by this section, upon the date of either event, and the earliest date if both events occur, no further bill credit pursuant to paragraph (2) of subdivision (b) may be earned. Only credit earned prior to that date shall be made to a benefiting account. (g) The Legislature finds and declares that credit for a benefiting account for the electricity output from the PVUSA are in the public interest in order to value the production of this unique, wholly renewable resource electricity generation facility located in, and owned in part by, the City of Davis. Because of the unique circumstances applicable only to the PVUSA a statute of general applicability cannot be enacted within the meaning of subdivision (b) of Section 16 of Article IV of the California Constitution. Therefore, this special statute is necessary. 2827. (a) The Legislature finds and declares that a program to provide net energy metering combined with net surplus compensation, co-energy metering, and wind energy co-metering for eligible customer-generators is one way to encourage substantial private investment in renewable energy resources, stimulate in-state economic growth, reduce demand for electricity during peak consumption periods, help stabilize California's energy supply infrastructure, enhance the continued diversification of California's energy resource mix, reduce interconnection and administrative costs for electricity suppliers, and encourage conservation and efficiency. (b) As used in this section, the following terms have the following meanings: (1) "Co-energy metering" means a program that is the same in all other respects as a net energy metering program, except that the local publicly owned electric utility has elected to apply a generation-to-generation energy and time-of-use credit formula as provided in subdivision (i). (2) "Electrical cooperative" means an electrical cooperative as defined in Section 2776. (3) "Electric utility" means an electrical corporation, a local publicly owned electric utility, or an electrical cooperative, or any other entity, except an electric service provider, that offers electrical service. This section shall not apply to a local publicly owned electric utility that serves more than 750,000 customers and that also conveys water to its customers. (4) "Eligible customer-generator" means a residential customer, small commercial customer as defined in subdivision (h) of Section 331, or commercial, industrial, or agricultural customer of an electric utility, who uses a solar or a wind turbine electrical generating facility, or a hybrid system of both, with a capacity of not more than one megawatt that is located on the customer's owned, leased, or rented premises, and is interconnected and operates in parallel with the electric grid, and is intended primarily to offset part or all of the customer's own electrical requirements. (5) "Net energy metering" means measuring the difference between the electricity supplied through the electric grid and the electricity generated by an eligible customer-generator and fed back to the electric grid over a 12-month period as described in subdivisions (c) and (h). (6) "Net surplus customer-generator" means an eligible customer-generator that generates more electricity during a 12-month period than is supplied by the electric utility to the eligible customer-generator during the same 12-month period. (7) "Net surplus electricity" means all electricity generated by an eligible customer-generator measured in kilowatthours over a 12-month period that exceeds the amount of electricity consumed by that eligible customer-generator. (8) "Net surplus electricity compensation" means a per kilowatthour rate offered by the electric utility to the net surplus customer-generator for net surplus electricity that is set by the ratemaking authority pursuant to subdivision (h). (9) "Ratemaking authority" means, for an electrical corporation or electrical cooperative, the commission, and for a local publicly owned electric utility, the local elected body responsible for setting the rates of the local publicly owned utility. (10) "Wind energy co-metering" means any wind energy project greater than 50 kilowatts, but not exceeding one megawatt, where the difference between the electricity supplied through the electric grid and the electricity generated by an eligible customer-generator and fed back to the electric grid over a 12-month period is as described in subdivision (h). Wind energy co-metering shall be accomplished pursuant to Section 2827.8. (c) (1) Every electric utility shall develop a standard contract or tariff providing for net energy metering, and shall make this standard contract or tariff available to eligible customer-generators, upon request, on a first-come-first-served basis until the time that the total rated generating capacity used by eligible customer-generators exceeds 5 percent of the electric utility's aggregate customer peak demand. Net energy metering shall be accomplished using a single meter capable of registering the flow of electricity in two directions. An additional meter or meters to monitor the flow of electricity in each direction may be installed with the consent of the eligible customer-generator, at the expense of the electric utility, and the additional metering shall be used only to provide the information necessary to accurately bill or credit the eligible customer-generator pursuant to subdivision (h), or to collect solar or wind electric generating system performance information for research purposes. If the existing electrical meter of an eligible customer-generator is not capable of measuring the flow of electricity in two directions, the eligible customer-generator shall be responsible for all expenses involved in purchasing and installing a meter that is able to measure electricity flow in two directions. If an additional meter or meters are installed, the net energy metering calculation shall yield a result identical to that of a single meter. An eligible customer-generator that is receiving service other than through the standard contract or tariff may elect to receive service through the standard contract or tariff until the electric utility reaches the generation limit set forth in this paragraph. Once the generation limit is reached, only eligible customer-generators that had previously elected to receive service pursuant to the standard contract or tariff have a right to continue to receive service pursuant to the standard contract or tariff. Eligibility for net energy metering does not limit an eligible customer-generator's eligibility for any other rebate, incentive, or credit provided by the electric utility, or pursuant to any governmental program, including rebates and incentives provided pursuant to the California Solar Initiative. (2) An electrical corporation shall include a provision in the net energy metering contract or tariff requiring that any customer with an existing electrical generating facility and meter who enters into a new net energy metering contract shall provide an inspection report to the electrical corporation, unless the electrical generating facility and meter have been installed or inspected within the previous three years. The inspection report shall be prepared by a California licensed contractor who is not the owner or operator of the facility and meter. A California licensed electrician shall perform the inspection of the electrical portion of the facility and meter. (3) (A) On an annual basis, beginning in 2003, every electric utility shall make available to the ratemaking authority information on the total rated generating capacity used by eligible customer-generators that are customers of that provider in the provider's service area and the net surplus electricity purchased by the electric utility pursuant to this section. (B) An electric service provider operating pursuant to Section 394 shall make available to the ratemaking authority the information required by this paragraph for each eligible customer-generator that is their customer for each service area of an electric corporation, local publicly owned electric utility, or electrical cooperative, in which the eligible customer-generator has net energy metering. (C) The ratemaking authority shall develop a process for making the information required by this paragraph available to electric utilities, and for using that information to determine when, pursuant to paragraphs (1) and (4), an electric utility is not obligated to provide net energy metering to additional eligible customer-generators in its service area. (4) An electric utility is not obligated to provide net energy metering to additional eligible customer-generators in its service area when the combined total peak demand of all electricity used by eligible customer-generators served by all the electric utilities in that service area furnishing net energy metering to eligible customer-generators exceeds 5 percent of the aggregate customer peak demand of those electric utilities. (5) By January 1, 2010, the commission, in consultation with the Energy Commission, shall submit a report to the Governor and the Legislature on the costs and benefits of net energy metering, wind energy co-metering, and co-energy metering to participating customers and nonparticipating customers and with options to replace the economic costs and benefits of net energy metering, wind energy co-metering, and co-energy metering with a mechanism that more equitably balances the interests of participating and nonparticipating customers, and that incorporates the findings of the report on economic and environmental costs and benefits of net metering required by subdivision (n). (d) Every electric utility shall make all necessary forms and contracts for net energy metering and net surplus electricity compensation service available for download from the Internet. (e) (1) Every electric utility shall ensure that requests for establishment of net energy metering and net surplus electricity compensation are processed in a time period not exceeding that for similarly situated customers requesting new electric service, but not to exceed 30 working days from the date it receives a completed application form for net energy metering service or net surplus electricity compensation, including a signed interconnection agreement from an eligible customer-generator and the electric inspection clearance from the governmental authority having jurisdiction. (2) Every electric utility shall ensure that requests for an interconnection agreement from an eligible customer-generator are processed in a time period not to exceed 30 working days from the date it receives a completed application form from the eligible customer-generator for an interconnection agreement. (3) If an electric utility is unable to process a request within the allowable timeframe pursuant to paragraph (1) or (2), it shall notify the eligible customer-generator and the ratemaking authority of the reason for its inability to process the request and the expected completion date. (f) (1) If a customer participates in direct transactions pursuant to paragraph (1) of subdivision (b) of Section 365 with an electric service provider that does not provide distribution service for the direct transactions, the electric utility that provides distribution service for the eligible customer-generator is not obligated to provide net energy metering or net surplus electricity compensation to the customer. (2) If a customer participates in direct transactions pursuant to paragraph (1) of subdivision (b) of Section 365 with an electric service provider, and the customer is an eligible customer-generator, the electric utility that provides distribution service for the direct transactions may recover from the customer's electric service provider the incremental costs of metering and billing service related to net energy metering and net surplus electricity compensation in an amount set by the ratemaking authority. (g) Except for the time-variant kilowatthour pricing portion of any tariff adopted by the commission pursuant to paragraph (4) of subdivision (a) of Section 2851, each net energy metering contract or tariff shall be identical, with respect to rate structure, all retail rate components, and any monthly charges, to the contract or tariff to which the same customer would be assigned if the customer did not use an eligible solar or wind electrical generating facility, except that eligible customer-generators shall not be assessed standby charges on the electrical generating capacity or the kilowatthour production of an eligible solar or wind electrical generating facility. The charges for all retail rate components for eligible customer-generators shall be based exclusively on the customer-generator's net kilowatthour consumption over a 12-month period, without regard to the eligible customer-generator's choice as to from whom it purchases electricity that is not self-generated. Any new or additional demand charge, standby charge, customer charge, minimum monthly charge, interconnection charge, or any other charge that would increase an eligible customer-generator's costs beyond those of other customers who are not eligible customer-generators in the rate class to which the eligible customer-generator would otherwise be assigned if the customer did not own, lease, rent, or otherwise operate an eligible solar or wind electrical generating facility is contrary to the intent of this section, and shall not form a part of net energy metering contracts or tariffs. (h) For eligible customer-generators, the net energy metering calculation shall be made by measuring the difference between the electricity supplied to the eligible customer-generator and the electricity generated by the eligible customer-generator and fed back to the electric grid over a 12-month period. The following rules shall apply to the annualized net metering calculation: (1) The eligible residential or small commercial customer-generator shall, at the end of each 12-month period following the date of final interconnection of the eligible customer-generator's system with an electric utility, and at each anniversary date thereafter, be billed for electricity used during that 12-month period. The electric utility shall determine if the eligible residential or small commercial customer-generator was a net consumer or a net surplus customer-generator during that period. (2) At the end of each 12-month period, where the electricity supplied during the period by the electric utility exceeds the electricity generated by the eligible residential or small commercial customer-generator during that same period, the eligible residential or small commercial customer-generator is a net electricity consumer and the electric utility shall be owed compensation for the eligible customer-generator's net kilowatthour consumption over that 12-month period. The compensation owed for the eligible residential or small commercial customer-generator's consumption shall be calculated as follows: (A) For all eligible customer-generators taking service under contracts or tariffs employing "baseline" and "over baseline" rates, any net monthly consumption of electricity shall be calculated according to the terms of the contract or tariff to which the same customer would be assigned to, or be eligible for, if the customer was not an eligible customer-generator. If those same customer-generators are net generators over a billing period, the net kilowatthours generated shall be valued at the same price per kilowatthour as the electric utility would charge for the baseline quantity of electricity during that billing period, and if the number of kilowatthours generated exceeds the baseline quantity, the excess shall be valued at the same price per kilowatthour as the electric utility would charge for electricity over the baseline quantity during that billing period. (B) For all eligible customer-generators taking service under contracts or tariffs employing time-of-use rates, any net monthly consumption of electricity shall be calculated according to the terms of the contract or tariff to which the same customer would be assigned, or be eligible for, if the customer was not an eligible customer-generator. When those same customer-generators are net generators during any discrete time-of-use period, the net kilowatthours produced shall be valued at the same price per kilowatthour as the electric utility would charge for retail kilowatthour sales during that same time-of-use period. If the eligible customer-generator's time-of-use electrical meter is unable to measure the flow of electricity in two directions, paragraph (1) of subdivision (c) shall apply. (C) For all eligible residential and small commercial customer-generators and for each billing period, the net balance of moneys owed to the electric utility for net consumption of electricity or credits owed to the eligible customer-generator for net generation of electricity shall be carried forward as a monetary value until the end of each 12-month period. For all eligible commercial, industrial, and agricultural customer-generators, the net balance of moneys owed shall be paid in accordance with the electric utility's normal billing cycle, except that if the eligible commercial, industrial, or agricultural customer-generator is a net electricity producer over a normal billing cycle, any excess kilowatthours generated during the billing cycle shall be carried over to the following billing period as a monetary value, calculated according to the procedures set forth in this section, and appear as a credit on the eligible commercial, industrial, or agricultural customer-generator's account, until the end of the annual period when paragraph (3) shall apply. (3) At the end of each 12-month period, where the electricity generated by the eligible customer-generator during the 12-month period exceeds the electricity supplied by the electric utility during that same period, the eligible customer-generator is a net surplus customer-generator and the electric utility shall, upon an affirmative election by the eligible customer-generator, either (A) provide net surplus electricity compensation for any net surplus electricity generated during the prior 12-month period, or (B) allow the eligible customer-generator to apply the net surplus electricity as a credit for kilowatthours subsequently supplied by the electric utility to the surplus customer-generator. For an eligible customer-generator that does not affirmatively elect to receive service pursuant to net surplus electricity compensation, the electric utility shall retain any excess kilowatthours generated during the prior 12-month period. The eligible customer-generator not affirmatively electing to receive service pursuant to net surplus electricity compensation shall not be owed any compensation for the net surplus electricity unless the electric utility enters into a purchase agreement with the eligible customer-generator for those excess kilowatthours. Every electric utility shall, by January 31, 2010, provide notice to eligible customer-generators that they are eligible to receive net surplus electricity compensation for net surplus electricity, that they must elect to receive net surplus electricity compensation, and that the 12-month period commences when the electric utility receives the eligible customer-generator's election. The commission may, for an electric utility that is an electrical corporation or electrical cooperative, adopt requirements for providing notice and the manner by which eligible customer-generators may elect to receive net surplus electricity compensation. (4) (A) The ratemaking authority shall, by January 1, 2011, establish a net surplus electricity compensation valuation to compensate the net surplus customer-generator for the value of net surplus electricity generated by the net surplus customer-generator. The commission shall establish the valuation in a ratemaking proceeding. The ratemaking authority for a local publicly owned electric utility shall establish the valuation in a public proceeding. The net surplus electricity compensation valuation shall be established so as to provide the net surplus customer-generator just and reasonable compensation for the value of net surplus electricity, while leaving other ratepayers unaffected. The ratemaking authority shall determine whether the compensation will include, where appropriate justification exists, either or both of the following components: (i) The value of the electricity itself. (ii) The value of the renewable attributes of the electricity. (B) In establishing the rate pursuant to subparagraph (A), the ratemaking authority shall ensure that the rate does not result in a shifting of costs between solar customer-generators and other bundled service customers. (5) (A) Upon adoption of the net surplus electricity compensation rate by the ratemaking authority, any renewable energy credit, as defined in Section 399.12, for net surplus electricity purchased by the electric utility shall belong to the electric utility. Any renewable energy credit associated with electricity generated by the eligible customer-generator that is utilized by the eligible customer-generator shall remain the property of the eligible customer-generator. (B) Upon adoption of the net surplus electricity compensation rate by the ratemaking authority, the net surplus electricity purchased by the electric utility shall count toward the electric utility's renewables portfolio standard annual procurement targets for the purposes of paragraph (1) of subdivision (b) of Section 399.15, or for a local publicly owned electric utility, the renewables portfolio standard annual procurement targets established pursuant to Section 387. (6) The electric utility shall provide every eligible residential or small commercial customer-generator with net electricity consumption and net surplus electricity generation information with each regular bill. That information shall include the current monetary balance owed the electric utility for net electricity consumed, or the net surplus electricity generated, since the last 12-month period ended. Notwithstanding this subdivision, an electric utility shall permit that customer to pay monthly for net energy consumed. (7) If an eligible residential or small commercial customer-generator terminates the customer relationship with the electric utility, the electric utility shall reconcile the eligible customer-generator's consumption and production of electricity during any part of a 12-month period following the last reconciliation, according to the requirements set forth in this subdivision, except that those requirements shall apply only to the months since the most recent 12-month bill. (8) If an electric service provider or electric utility providing net energy metering to a residential or small commercial customer-generator ceases providing that electric service to that customer during any 12-month period, and the customer-generator enters into a new net energy metering contract or tariff with a new electric service provider or electric utility, the 12-month period, with respect to that new electric service provider or electric utility, shall commence on the date on which the new electric service provider or electric utility first supplies electric service to the customer-generator. (i) Notwithstanding any other provisions of this section, the following provisions shall apply to an eligible customer-generator with a capacity of more than 10 kilowatts, but not exceeding one megawatt, that receives electric service from a local publicly owned electric utility that has elected to utilize a co-energy metering program unless the local publicly owned electric utility chooses to provide service for eligible customer-generators with a capacity of more than 10 kilowatts in accordance with subdivisions (g) and (h): (1) The eligible customer-generator shall be required to utilize a meter, or multiple meters, capable of separately measuring electricity flow in both directions. All meters shall provide time-of-use measurements of electricity flow, and the customer shall take service on a time-of-use rate schedule. If the existing meter of the eligible customer-generator is not a time-of-use meter or is not capable of measuring total flow of energy in both directions, the eligible customer-generator shall be responsible for all expenses involved in purchasing and installing a meter that is both time-of-use and able to measure total electricity flow in both directions. This subdivision shall not restrict the ability of an eligible customer-generator to utilize any economic incentives provided by a governmental agency or an electric utility to reduce its costs for purchasing and installing a time-of-use meter. (2) The consumption of electricity from the local publicly owned electric utility shall result in a cost to the eligible customer-generator to be priced in accordance with the standard rate charged to the eligible customer-generator in accordance with the rate structure to which the customer would be assigned if the customer did not use an eligible solar or wind electrical generating facility. The generation of electricity provided to the local publicly owned electric utility shall result in a credit to the eligible customer-generator and shall be priced in accordance with the generation component, established under the applicable structure to which the customer would be assigned if the customer did not use an eligible solar or wind electrical generating facility. (3) All costs and credits shall be shown on the eligible customer-generator's bill for each billing period. In any months in which the eligible customer-generator has been a net consumer of electricity calculated on the basis of value determined pursuant to paragraph (2), the customer-generator shall owe to the local publicly owned electric utility the balance of electricity costs and credits during that billing period. In any billing period in which the eligible customer-generator has been a net producer of electricity calculated on the basis of value determined pursuant to paragraph (2), the local publicly owned electric utility shall owe to the eligible customer-generator the balance of electricity costs and credits during that billing period. Any net credit to the eligible customer-generator of electricity costs may be carried forward to subsequent billing periods, provided that a local publicly owned electric utility may choose to carry the credit over as a kilowatthour credit consistent with the provisions of any applicable contract or tariff, including any differences attributable to the time of generation of the electricity. At the end of each 12-month period, the local publicly owned electric utility may reduce any net credit due to the eligible customer-generator to zero. (j) A solar or wind turbine electrical generating system, or a hybrid system of both, used by an eligible customer-generator shall meet all applicable safety and performance standards established by the National Electrical Code, the Institute of Electrical and Electronics Engineers, and accredited testing laboratories, including Underwriters Laboratories and, where applicable, rules of the commission regarding safety and reliability. A customer-generator whose solar or wind turbine electrical generating system, or a hybrid system of both, meets those standards and rules shall not be required to install additional controls, perform or pay for additional tests, or purchase additional liability insurance. (k) If the commission determines that there are cost or revenue obligations for an electrical corporation, as defined in Section 218, that may not be recovered from customer-generators acting pursuant to this section, those obligations shall remain within the customer class from which any shortfall occurred and may not be shifted to any other customer class. Net energy metering and co-energy metering customers shall not be exempt from the public goods charges imposed pursuant to Article 7 (commencing with Section 381), Article 8 (commencing with Section 385), or Article 15 (commencing with Section 399) of Chapter 2.3 of Part 1. In its report to the Legislature, the commission shall examine different methods to ensure that the public goods charges remain nonbypassable. (l) A net energy metering, co-energy metering, or wind energy co-metering customer shall reimburse the Department of Water Resources for all charges that would otherwise be imposed on the customer by the commission to recover bond-related costs pursuant to an agreement between the commission and the Department of Water Resources pursuant to Section 80110 of the Water Code, as well as the costs of the department equal to the share of the department's estimated net unavoidable power purchase contract costs attributable to the customer. The commission shall incorporate the determination into an existing proceeding before the commission, and shall ensure that the charges are nonbypassable. Until the commission has made a determination regarding the nonbypassable charges, net energy metering, co-energy metering, and wind energy co-metering shall continue under the same rules, procedures, terms, and conditions as were applicable on December 31, 2002. (m) In implementing the requirements of subdivisions (k) and (l), an eligible customer-generator shall not be required to replace its existing meter except as set forth in paragraph (1) of subdivision (c), nor shall the electric utility require additional measurement of usage beyond that which is necessary for customers in the same rate class as the eligible customer-generator. (n) It is the intent of the Legislature that the Treasurer incorporate net energy metering, including net surplus electricity compensation, co-energy metering, and wind energy co-metering projects undertaken pursuant to this section as sustainable building methods or distributive energy technologies for purposes of evaluating low-income housing projects. 2827.5. The Legislature finds and declares that the repeal of the provisions of the net metering program for large customers merely reflects a legislative desire to revisit and more closely evaluate the cumulative value and effect of the state's policy regarding renewable energy sources on the economics of investment in solar and wind sources for large net metering customers and to ensure further legislative discussion regarding this issue. 2827.7. Generation eligible for net energy metering that has all local and state permits required to commence construction on or before December 31, 2002, and has completed construction on or before September 30, 2003, shall be entitled, regardless of any change in customer or ownership of the energy system, for the life of the installation, to the net energy metering terms in effect on the date the local and state permits were acquired. 2827.8. Notwithstanding any other provisions of this article, the following provisions apply to an eligible customer-generator utilizing wind energy co-metering with a capacity of more than 50 kilowatts, but not exceeding one megawatt, unless approved by the electric service provider. (a) The eligible customer-generator shall be required to utilize a meter, or multiple meters, capable of separately measuring electricity flow in both directions. All meters shall provide "time-of-use" measurements of electricity flow, and the customer shall take service on a time-of-use rate schedule. If the existing meter of the eligible customer-generator is not a time-of-use meter or is not capable of measuring total flow of energy in both directions, the eligible customer-generator is responsible for all expenses involved in purchasing and installing a meter that is both time-of-use and able to measure total electricity flow in both directions. This subdivision shall not restrict the ability of an eligible customer-generator to utilize any economic incentives provided by a government agency or the electric service provider to reduce its costs for purchasing and installing a time-of-use meter. (b) The consumption of electricity from the electric service provider for wind energy co-metering by an eligible customer-generator shall be priced in accordance with the standard rate charged to the eligible customer-generator in accordance with the rate structure to which the customer would be assigned if the customer did not use an eligible wind electrical generating facility. The generation of electricity provided to the electric service provider shall result in a credit to the eligible customer-generator and shall be priced in accordance with the generation component, excluding surcharges to cover the purchase of power by the Department of Water Resources, established under the applicable structure to which the customer would be assigned if the customer did not use an eligible wind electrical generating facility. 2827.9. (a) (1) The Legislature finds and declares that a pilot program to provide net energy metering for eligible biogas digester customer-generators would enhance the continued diversification of California's energy resource mix and would encourage the installation of livestock air emission controls that the State Air Resources Board believes may produce multiple environmental benefits. (2) The Legislature further finds and declares that the net energy metering pilot program authorized pursuant to this section for eligible biogas digester customer-generators, which nets out generation charges against generation charges on a time-of-use basis, furthers the intent of Chapter 7 of the Statutes of 2001, First Extraordinary Session, by facilitating the implementation of energy efficiency programs in order to reduce consumption of energy, reduce the costs associated with energy demand, and achieve a reduction in peak electricity demand. (b) As used in this section, the following definitions apply: (1) "Electrical corporation" means an electrical corporation, as defined in Section 218. (2) (A) "Eligible biogas digester customer-generator" means a customer of an electrical corporation that meets both of the following criteria: (i) Uses a biogas digester electrical generating facility with a capacity of not more than one megawatt that is located on or adjacent to the customer's owned, leased, or rented premises, is interconnected and operates in parallel with the electric grid, and is sized to offset part or all of the eligible biogas digester customer-generator's own electrical requirements. (ii) Is the recipient of local, state, or federal funds, or who self-finances pilot projects designed to encourage the development of eligible biogas digester electrical generating facilities. (B) Notwithstanding subparagraph (A), up to three large biogas digester electrical generating facilities with a generating capacity of more than one megawatt and not more than 10 megawatts, otherwise meeting the criteria of this section, shall be eligible for participation in the pilot program. (3) "Eligible biogas digester electrical generating facility" means a generating facility used to produce electricity by either a manure methane production project or as a byproduct of the anaerobic digestion of biosolids and animal waste. (4) "Net energy metering" means measuring the difference between the electricity supplied through the electric grid and the difference between the electricity generated by an eligible biogas digester customer-generator and fed back to the electric grid over a 12-month period as described in subdivision (e). Net energy metering shall be accomplished using a time-of-use meter capable of registering the flow of electricity in two directions. If the existing electrical meter of an eligible biogas digester customer-generator is not capable of measuring the flow of electricity in two directions, the eligible biogas digester customer-generator shall be responsible for all expenses involved in purchasing and installing a meter that is able to measure electricity flow in two directions. If an additional meter or meters are installed, the net energy metering calculation shall yield a result identical to that of a time-of-use meter. (c) Every electrical corporation shall file with the commission a standard tariff providing for net energy metering for eligible biogas digester customer-generators, consistent with this section. Every electrical corporation shall make this tariff available to eligible biogas digester customer-generators upon request, on a first-come-first-served basis, until the combined statewide cumulative rated generating capacity used by the eligible biogas digester customer-generators in the service territories of the three largest electrical corporations in the state reaches 50 megawatts. An eligible biogas digester customer-generator shall be eligible for the tariff for the life of the eligible biogas digester electrical generating facility. (d) Each net energy metering contract or tariff shall be identical, with respect to rate structure, all retail rate components, and any monthly charges, to the contract or tariff to which the same customer would be assigned if the customer was not an eligible biogas digester customer-generator, except as set forth in subdivision (e). Any new or additional demand charge, standby charge, customer charge, minimum monthly charge, interconnection charge, or other charge that would increase an eligible biogas digester customer-generator's costs beyond those of other customers in the rate class to which the eligible biogas digester customer-generator would otherwise be assigned are contrary to the intent of this legislation, and shall not form a part of net energy metering tariffs. (e) The net energy metering calculation shall be made by measuring the difference between the electricity supplied to the eligible customer-generator and the electricity generated by the eligible customer-generator and fed back to the electric grid over a 12-month period. The following rules shall apply to the annualized metering calculation: (1) The eligible biogas digester customer-generator shall, at the end of each 12-month period following the date of final interconnection of the eligible biogas digester customer-generator's system with an electrical corporation, and at each anniversary date thereafter, be billed for electricity used during that period. The electrical corporation shall determine if the eligible biogas digester customer-generator was a net consumer or a net producer of electricity during that period. For purposes of determining if the biogas digester customer-generator was a net consumer or a net producer of electricity during that period, the electrical corporation shall aggregate the electrical load of a dairy operation under the same ownership, including, but not limited to, the electrical load attributable to milking operations, milk refrigeration, and water pumping located on property adjacent or contiguous to the dairy. Each aggregated account shall be billed and measured according to a time-of-use rate schedule. (2) At the end of each 12-month period, where the electricity supplied during the period by the electrical corporation exceeds the electricity generated by the eligible biogas digester customer-generator during that same period, the eligible biogas digester customer-generator is a net electricity consumer and the electrical corporation shall be owed compensation for the eligible biogas digester customer-generator's net kilowatthour consumption over that same period. The compensation owed for the eligible biogas digester customer-generator's consumption shall be calculated as follows: (A) The generation charges for any net monthly consumption of electricity shall be calculated according to the terms of the tariff to which the same customer would be assigned to or be eligible for if the customer was not an eligible biogas digester customer-generator. When those eligible biogas digester customer-generators are net generators during any discrete time-of-use period, the net kilowatthours produced shall be valued at the same price per kilowatthour as the electrical corporation would charge for retail kilowatthour sales for generation, exclusive of any surcharges, during that same time-of-use period. If the eligible biogas digester customer-generator's time-of-use electrical meter is unable to measure the flow of electricity in two directions, paragraph (4) of subdivision (b) shall apply. All other charges, other than generation charges, shall be calculated in accordance with the eligible biogas digester customer-generator's applicable tariff and based on the total killowatthours delivered by the electrical corporation to the eligible biogas digester customer-generator. To the extent that charges for transmission and distribution services are recovered through demand charges in any particular month, no standby reservation charges shall apply in that monthly billing cycle. (B) The net balance of moneys owed shall be paid in accordance with the electrical corporation's normal billing cycle. (3) At the end of each 12-month period, where the electricity generated by the eligible biogas digester customer-generator during the 12-month period exceeds the electricity supplied by the electrical corporation during that same period, the eligible biogas digester customer-generator is a net electricity producer and the electrical corporation shall retain any excess kilowatthours generated during the prior 12-month period. The eligible biogas digester customer-generator shall not be owed any compensation for those excess kilowatthours. (4) If an eligible biogas digester customer-generator terminates service with the electrical corporation, the electrical corporation shall reconcile the eligible biogas digester customer-generator's consumption and production of electricity during any 12-month period. (f) No biogas digester electrical generating facility shall be eligible for participation in the tariff established pursuant to this section, that has not commenced operation by December 31, 2009. A biogas digester customer-generator shall be eligible for the tariff established pursuant to this section, only for the operating life of the eligible biogas digester electrical generating facility. (g) No biogas digester electrical generating facility that is subject to the best available control technology (BACT) requirements shall be eligible for participation in the tariff pursuant to this section unless the biogas digester electrical generating facility has installed the best available control technology as required by the regional air pollution control district at the time of installation to ensure the maximum feasible reductions in toxic and criteria pollutants. (h) On or before December 31, 2008, the commission, in collaboration with the State Air Resources Board, shall report to the Legislature all of the following information: (1) The impact of the pilot program on emissions of air pollutants. (2) The impact of the pilot program on the reliability of the transmission and distribution grid. (3) The impact of the pilot program on ratepayers. 2827.10. (a) As used in this section, the following terms have the following meanings: (1) "Electrical corporation" means an electrical corporation, as defined in Section 218. (2) "Eligible fuel cell electrical generating facility" means a facility that includes the following: (A) Integrated powerplant systems containing a stack, tubular array, or other functionally similar configuration used to electrochemically convert fuel to electric energy. (B) An inverter and fuel processing system where necessary. (C) Other plant equipment, including heat recovery equipment, necessary to support the plant's operation or its energy conversion. (3) "Eligible fuel cell customer-generator" means a customer of an electrical corporation that meets all the following criteria: (A) Uses a fuel cell electrical generating facility with a capacity of not more than one megawatt that is located on or adjacent to the customer's owned, leased, or rented premises, is interconnected and operates in parallel with the electric grid while the grid is operational or in a grid independent mode when the grid is nonoperational, and is sized to offset part or all of the eligible fuel cell customer-generator's own electrical requirements. (B) Is the recipient of local, state, or federal funds, or who self-finances projects designed to encourage the development of eligible fuel cell electrical generating facilities. (C) Uses technology that meets the definition of an "ultra-clean and low-emission distributed generation" in subdivision (a) of Section 353.2. (4) "Net energy metering" has the same meaning as that term is defined in Section 2827.9. (b) Every electrical corporation shall, not later than March 1, 2004, file with the commission a standard tariff providing for net energy metering for eligible fuel cell customer-generators, consistent with this section. Every electrical corporation shall make this tariff available to eligible fuel cell customer-generators upon request, on a first-come-first-served basis, until the total cumulative rated generating capacity used by the eligible fuel cell customer-generators equals 45 megawatts within the service territory of the electrical corporation for an electrical corporation with a peak demand above 10,000 megawatts, or equals 22.5 megawatts within the service territory of the electrical corporation for an electrical corporation with a peak demand of 10,000 megawatts or below. The combined statewide cumulative rated generating capacity used by the eligible fuel cell customer-generators in the service territories of all electrical corporations in the state may not exceed 112.5 megawatts. (c) In determining the eligibility for the cumulative rated generating capacity within an electrical service area, preference shall be given to facilities which, at the time of installation, are located in a community with significant exposure to air contaminants or localized air contaminants, or both, including, but not limited to, communities of minority populations or low-income populations, or both, based on the ambient air quality standards established pursuant to Section 39607 of the Health and Safety Code. (d) Each net energy metering contract or tariff shall be identical, with respect to rate structure, all retail rate components, and any monthly charges, to the contract or tariff to which the customer would be assigned if the customer was not an eligible fuel cell customer-generator. Any new or additional demand charge, standby charge, customer charge, minimum monthly charge, interconnection charge, or other charge that would increase an eligible fuel cell customer-generator's costs beyond those of other customers in the rate class to which the eligible fuel cell customer-generator would otherwise be assigned are contrary to the intent of the Legislature in enacting the act adding this section, and may not form a part of net energy metering tariffs. (e) The net metering calculation shall be carried out in accordance with Section 2827.9. (f) A fuel cell electrical generating facility shall not be eligible for participation in the tariff established pursuant to this section unless it commenced operation before January 1, 2014. A fuel cell customer-generator shall be