§ 23-4-502 - Filing interim rate schedule.
23-4-502. Filing interim rate schedule.
Any public utility as defined in 23-1-101 may recover all costs and expenses reasonably incurred by such a utility as a direct result of legislative or regulatory requirements relating to the protection of the public health, safety, and the environment by filing with the Arkansas Public Service Commission, no more frequently than once every six (6) months, an interim rate schedule which would impose a separate surcharge in addition to its currently effective rates until the implementation of new rate schedules in connection with the next general rate filing of the utility wherein such additional expenditures can be included in the utility's base rate schedules.