Sec. 43.90.210. - Amendment of or modification to the project plan.
Subject to the approval of the commissioners, a licensee may amend or modify its project plan if the amendment or modification improves the net present value of the project to the state, is necessary because of an order or requirement by a regulatory agency with jurisdiction over the project or by the Alaska Oil and Gas Conservation Commission, or is necessary because of changed circumstances outside the licensee's control and not reasonably foreseeable before the license was issued. An amendment or modification approved under this section must be consistent with the requirements of AS 43.90.130 and, except for an amendment or modification required because of an order or requirement of a regulatory agency with jurisdiction over the project or by the Alaska Oil and Gas Conservation Commission, may not substantially diminish the value of the project to the state or the project's likelihood of success.